Underpinning Calculator

Concrete and rebar for underpinning beams in one go.

Quick answer

With the default inputs: Beam length per segment 3 m · Beam width 0.5 m · Beam depth 0.7 m etc.Concrete 6.30 m³

Use your own dimensions ↓

Inputs

Excavated in alternate bays, usually 1-2.5 m each
strips

Result

Concrete
6.30m³
Concrete per segment1.05m³
Rebar693kg
Reinforcement ratio110kg/m³
How this is worked out

Underpinning excavates an existing footing in alternate bays and casts new beams that carry the load down to a deeper, sounder bearing layer - used when a nearby excavation disturbs the ground or the existing footing is under-strength. Work must be in alternate bays: cast and cure one bay before excavating the next. Never undermine the whole footing at once or the structure loses support and cracks or collapses. Bays are usually 1-2.5 m long by soil and load. Underpinning beams carry more steel than ordinary beams (~110 kg/m³) for the concentrated reactions during excavation.

Next up: High Strength Bolt Torque Calculator · Plaster and Render Calculator

Formula

Concrete per segmentV₁ = L·B·H
Total concreteV = V₁·segments
RebarW = V·110 (kg)
3 m × 0.5 m × 0.7 m × 6 segments: 1.05 m³ per segment, 6.30 m³ total, ~693 kg rebar.

Quantities by number of segments (3.0 × 0.5 × 0.7 m needle beam, 110 kg/m³)

SegmentsConcrete (m³)Rebar (kg)Per segment (m³)Where it fits
44.204621.05Short wall, one-sided underpinning
66.306931.05This tool's default - a typical run of wall
88.409241.05Longer wall with more open segments
1010.5011551.05Long wall, or where the segment has to be shorter

Choosing the underpinning method - a needle beam is not the only answer

MethodFitsAdvantageMain risk
Needle beam in open segmentsBrick or block strip footings, low-riseCheap, simple, done in placeWrong sequence removes the support
Pile underpinning (pit or pier)Insufficient capacity, load must reach good groundBig gain in capacityDeep pits that need their own support
Widening the footingFooting too narrow, ground still soundKeeps the underside levelThe old-to-new concrete interface can debond if not prepared
Grouting (compaction / fracture)Sand and gravel, settlement already under wayNo work to the superstructure, fastVariable results - trial and testing are essential

Basis

FAQ

Why must underpinning be done in alternate bays?
Because the existing footing continuously carries the structure above. Undermine it all at once and the support vanishes - walls and columns lose bearing, cracking or even collapsing locally. Alternate bays keep most of the footing supported at all times; once a new bay is cast and cured it takes over, and the next bay is excavated. This is the crux of underpinning, not an optional sequencing choice.
When is underpinning needed?
Two cases: a nearby excavation (deep pit, metro, utilities) destabilises or de-rates the existing footing, or the building shows settlement cracks from an under-strength footing. The trigger is the zone of influence - once a nearby excavation goes below the existing footing level, underpinning or support should be assessed, not left until cracks appear.
Why must underpinning be done in alternate open segments?
The needle beam has to take over from the piece of footing you have removed. Open the whole run at once and the wall above loses every support point: a brick wall cracks immediately and, in the bad case, collapses. It is the most common and most lethal underpinning failure. The sequence is alternate bays: dig 1, cast 1, wait for strength, then dig 3 and cast 3, and only come back to 2 and 4 when the rest is done. Segment length follows the integrity of the wall and the load, typically 1.5-3.0 m.
Where does the 110 kg/m³ reinforcement figure come from - can I quote on it?
It is an order-of-magnitude figure for needle beams, not a code value. The beam is shallow and short but the reinforcement ratio runs high, usually governed by detailing rather than by bending, because the depth is limited by the footing. Real values scatter between 90 and 140 kg/m³ depending on depth, span, seismic detailing and whether it carries a concentrated wall load. Use 110 for a budget; price the settlement off the reinforcement drawing. This tool estimates only and does not replace structural design.
Underpinning or grouting - how do I choose?
Ask whether the load has to be carried down. A needle beam is a structural member: it takes the load around the removed or inadequate piece of footing and passes it to either side or to better ground, and it solves a capacity problem cleanly. Grouting improves the soil - it raises strength and stiffness and reduces settlement - but it is an areal improvement, not a load path, and its results are variable and hard to verify. So: footing too narrow or too shallow means underpinning or widening; loose ground with settlement already under way means grouting; both means pile underpinning, taking the load straight to the deeper stratum.
What should be monitored during underpinning?
Four things, none optional. Settlement points on the wall being underpinned and on both sides, read daily, and stop work for analysis at 5 mm of differential. Crack monitoring on the existing wall, with tell-tales or gauges, to see whether old cracks are moving. Settlement of the adjacent footing, because underpinning redistributes load and the neighbour can go down instead. And observation of the open face for soil boiling or seepage. The readings must be taken and reviewed the same day - next-day data is useless, because underpinning failures happen within hours.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Underpinning Calculator. 2026-10-25. https://jianzhujisuan.com/en/underpinning

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.