Waterproofing Area and Membrane Calculator

Total area with upstands, membrane rolls and primer.

Inputs

m²
m
Wall bases, pipe collars, parapet upstands
m
0.3 wet rooms, 1.8 shower walls, 0.25+ parapets
%
10 cm laps minimum, 15% on complex details
m
m

Result

Formula

Upstand areaperimeter × height
Total areaflat area + upstands
With lapstotal × (1 + lap %)
Per rollwidth × length
Rollsceil(quantity ÷ per roll)
Detailstotal × 10%
100 m² flat with 40 m of upstand at 0.3 m, 12% laps and 1 × 10 m rolls: 12.00 m² of upstand, 112.00 m² total, 125.44 m² with laps, 13 rolls and 33.6 kg of primer.

FAQ

Why does waterproofing always come out larger than expected?
Because upstands and details get forgotten. A 100 m² wet room adds a dozen square metres at 300 mm wall bases, doubling where shower walls go to 1.8 m, and corner, collar and outlet details add more — typically 30-50% over the flat area. Quoting from floor area alone loses money.
How much lap is needed?
By material: SBS membrane needs at least 100 mm along the length and 150 mm across; self-adhesive can be less but not under 80 mm; liquid membranes have no laps but need an extra coat. Laps are where leaks start, so codes also require them staggered — end laps of adjacent rolls at least 500 mm apart, never forming a continuous cross joint.
How is waterproofing inspected?
With a flood or spray test. Wet rooms are flooded 20 mm deep for 24 hours, 48 under some codes, and checked from below for leaks; roofs get a two-hour spray or 24-hour flood. Critically, test after the membrane and before the finish — once tiling is done the leak path is hidden and repair means breaking tiles.

Related calculators

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.