Steel Sheet Pile Cofferdam Calculator
Perimeter to pile count to total weight, by Larssen section.
Also known as cofferdam design · water exclusion · sheet pile cofferdam
With the default inputs: Cofferdam length 20 m · Cofferdam width 12 m · Sheet pile section Larssen IV etc.Sheet piles 160 bars
Use your own dimensions ↓Inputs
Result
| Cofferdam perimeter | 64.0m |
| Total pile length | 1920m |
| Unit weight | 76.1kg/m |
| Total weight | 146112kg |
| Tonnes | 146.1t |
How this is worked out
A steel sheet pile cofferdam drives Larssen piles around the perimeter, interlocked to cut off water. Effective width is about 0.4 m, count = perimeter ÷ 0.4 rounded up, with corner piles to close the ring. Pile length = water depth + embedment + freeboard; embedment must satisfy base heave, seepage and overall stability, not just reach the bed. Weight follows the section (III 60, IV 76.1, V 105, VI 120 kg/m). After closing, dewatering pumps are sized separately from seepage and are not included.
Next up: Scaffold Tie Calculator · Scaffolding Calculator
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Perimeter | P = 2 × (length + width) |
| Pile count | n = ⌈P ÷ 0.4⌉ |
| Total length | L = n × pile length |
| Total weight | W = L × unit weight (kg/m) |
How to work it out
- Perimeter = 2 × (length + width); sheets run continuously around it, count = ⌈perimeter ÷ unit width⌉.
- Larssen sheets are about 0.4 m wide; pick the section by stiffness: type III 60 kg/m, type IV 76.1 kg/m.
- Total weight = count × length × unit weight, for rental or purchase take-off.
- Internal bracing (waler + struts / corner braces) must be checked; the water and earth pressure is carried by the bracing system.
- Sheet length must satisfy bottom seepage stability (against piping and heave), not just reach the pump-down level.
Where it goes wrong
- Undersized section - the wall is too flexible, deforms, the interlocks open and the cofferdam leaks.
- Sheets too short - a short seepage path causes piping and heave, sand boils up inside, and the cofferdam fails.
- Missing or over-spaced internal bracing - a sheet wall is flexible and depends entirely on bracing; without it the wall bulges and fails.
Material and cost
Steel sheet piles are rented on a tonne or metre basis and are the economical choice for temporary cofferdams and shallow pits; they are pulled and recovered after use, far cheaper than one-shot retention (bored piles, diaphragm wall) for temporary works.
On site
- Control driving verticality and interlock engagement - a skewed sheet will not close the interlock and leaks.
- Seal the interlocks (asphalt, bentonite) to cut seepage.
- Watch seepage and movement after pumping; if seepage suddenly rises, back-flood and inspect at once.
Basis
- EN 1997-1:2004, Section 9 (retaining structures) and 10 (hydraulic failure)
- BS EN 12063:1999 Execution of special geotechnical work — Sheet-pile walls
- CIRIA C750 Groundwater control — design and practice (2nd edition)
- EM 1110-2-2503 Design of sheet pile cellular cofferdams and retaining structures (US)
FAQ
Larssen III or IV?
What to watch when dewatering a cofferdam?