Scaffold Dismantle Sequence Calculator

Lifts to strip, allowable step height, and where the raking props start.

Quick answer

With the default inputs: Scaffold height 20 m · Lift height 1.8 m · Bay length 1.5 m etc.Lifts to dismantle 12 lifts

Use your own dimensions ↓

Inputs

Result

Lifts to dismantle
12lifts
Max step between sections3.60m
Prop level per code6.50m
Prop lift from bottom4lifts
Elevation of that lift7.20m
Lifts left after props4lifts
Total ties (3 lifts x 3 bays)180pcs
Tie rows4courses
Elevation area4000m²
How this is worked out

Per JGJ 130-2011 clause 7.4: dismantling must proceed lift by lift from the top down, never from two levels at once; ties must come out lift by lift with the scaffold, never a whole floor or several floors ahead of the frame; where adjacent sections differ by more than two lifts, extra ties must be added (this tool gives that two-lift figure in metres); and when the remaining frame reaches the last full-length standard, about 6.5 m, temporary raking props must be installed before the ties are removed. Work must follow an approved method statement, with the coupler connections, ties and bracing checked first, the sequence reviewed and signed off, and the crew briefed. Components must never be thrown to the ground. This tool checks geometry only - the sequence itself must come from the method statement.

Next up: Scaffold Tie Calculator · Scaffolding Calculator

Formula

Lifts = ceil(height ÷ lift height)
Max step = 2 × lift height (add ties beyond this)
Prop level = about 6.5 m (JGJ 130 7.4.3)
Prop lift = ceil(6.5 ÷ lift height)
Ties = ceil(perimeter ÷ (3×bay)) × ceil(height ÷ (3×lift))
200 m perimeter, 20 m high, 1.8 m lifts, 1.5 m bays: 12 lifts to strip. Where two sections differ by more than 3.6 m, extra ties are required. At the fourth lift from the bottom (7.2 m elevation, roughly 6.5 m of frame left) temporary raking props go in before the ties at that level come out. 45 ties per row over 4 rows gives 180, and every one must come out lift by lift with the frame.

How to work it out

  1. Count the lifts first: height ÷ lift height, rounded up. 20 m at 1.8 m lifts is 12 lifts — that is how many levels come down.
  2. Decide the sections: adjacent sections must not differ by more than two lifts (3.6 m at 1.8 m lifts). Beyond that, extra ties must be added to that section, otherwise the two halves behave independently and the joint goes first.
  3. Fix the order within each lift: boards off, then netting and toe boards, then transoms, then ledgers, then standards. Never pull a member out of the middle and never work at two levels at once.
  4. Take the ties out lift by lift, with the frame. Never strip a whole floor or several floors of ties and come back for the scaffold later — that is the single most common cause of dismantling collapses.
  5. When only about 6.5 m is left (roughly the fourth lift at 1.8 m lifts, 7.2 m elevation), install temporary raking props on the outside first, then remove the ties at that level. That stub has no frame above it and almost no ties left, which makes it the least stable it will ever be.
  6. Lower components on a rope or in a chute — never throw them. Sort tubes, couplers and boards on the ground and count them the same day, so shortages are found while the crew is still on site.

Where it goes wrong

On site

Basis

FAQ

Why can't the ties come out first?
Ties are the only members that transfer horizontal load into the structure - they give the scaffold its wind and overturning resistance. Strip a whole floor or several floors of ties and the frame becomes a free-standing set of tubes; self-weight plus the crew and stacked material on it is enough to topple it. Investigation reports into dismantling collapses repeatedly cite exactly this: the ties were removed a floor or more ahead of the frame, so it lost its restraint. That is why the code makes ties-out-with-the-lift a mandatory requirement.
Why prop the frame at about 6.5 m, of all heights?
Ties are densest at the top and get scarcer as you strip downwards, so restraint falls away. When only the last full-length standard is left, roughly 6.5 m, that stub has no weight of frame above it and almost no ties left - which is the least stable it will ever be. The code therefore requires temporary raking props from the outside first, then the ties at that level. Props are normally set at 45 to 60 degrees to the ground, footed on firm bearing.
Does dismantling need a method statement?
Yes. Clause 7.4.1 requires dismantling to follow an approved method statement, and four things before starting: check the coupler connections, ties and bracing against the design; revise the sequence and measures in the method statement in the light of that check and get it approved; brief the crew; and clear debris from the scaffold and obstructions from the ground. A named person must direct the work. Land-based tubular scaffolds 24 m and above are classified as high-risk works, so the statement needs sign-off from the contractor's technical lead and the chief supervising engineer.

What to calculate next

These jobs are done back to back on site — follow the steps to work through the whole sequence.

Scaffolding: quantity to costStep 4 of 5

  1. 1Scaffolding Calculator
  2. 2Full Scaffold Material Calculator
  3. 3Scaffold Tie Calculator
  4. 4Scaffold Dismantle Sequence Calculator
  5. 5Scaffolding Cost Calculator

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Scaffold Dismantle Sequence Calculator. 2026-10-25. https://jianzhujisuan.com/en/scaffold-dismantle

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.