Concrete Pumping Calculator

Real output, pour duration and the truck fleet needed to keep the pump fed.

Quick answer

With the default inputs: Volume to place 100 m³ · Theoretical output 60 m³/h · Efficiency factor 0.6 etc.Real output 36.0 m³/h

Edit the inputs below to recalculate.

Inputs

m³
m³/h
Trailer 40-80, truck-mounted 60-90, boom pump 80-120
Allowing for set-up, cleaning, waiting and moving, usually 0.5-0.7
m³
min
Load, travel, discharge and return

Result

Real output
36.0m³/h
Pour duration2.78h
In minutes167min
Trucks per hour4.00loads/h
Trucks to keep pace3units
Recommended fleet4units
Arrival interval15.0min
Total loads12loads

Fleet size is round trip divided by arrival interval, excluding traffic and plant queues. Add one spare: a pump left waiting more than 30 minutes risks a cold joint.

Formula

Real outputQ = Q_theoretical × efficiency
Durationt = V ÷ Q
Trucks per hourn = Q ÷ truck capacity
FleetN = ceil(n × cycle ÷ 60)
Arrival intervalΔt = 60 ÷ n minutes
100 m³ with a 60 m³/h pump at 0.6 efficiency, 9 m³ trucks and a 40-minute cycle: 36 m³/h real output, 2.78 hours of placing, 4 trucks per hour, 3 trucks needed (4 recommended) arriving every 15 minutes.

How to work it out

  1. Actual output = rated output × efficiency. Take 0.65 with a clear site and few pipe moves, 0.5 with many bends or a long vertical run, 0.45-0.55 with a placing boom.
  2. Duration t = total volume ÷ actual output, then divide by productive hours per shift (about 8 h less 1 h for repositioning) to get shifts.
  3. Arrival rate needed to keep the pump fed: n = actual output ÷ truck capacity, in trucks per hour.
  4. Trucks in the cycle N = ⌈n × cycle time ÷ 60⌉, with the cycle covering loading, travel, waiting, discharge and return.
  5. Arrival interval Δt = 60 ÷ n minutes; it must match the real truck spacing or the pump sits waiting.

Where it goes wrong

Material and cost

Boom pump hire runs 8,000-12,000 per shift; a trailer pump with placing boom 5,000-8,000; trucks 800-1,200 each including haul within 20 km. Pumping is charged at 25-45 per m³, with a high-rise premium.

On site

Basis

FAQ

Why an efficiency factor of 0.6?
Rated output assumes full load and an ideal pipeline. Real work loses time to set-up, flushing, moving the line, waiting for trucks and voltage swings, so 50-70% is typical. Pressure losses add up as roughly 1 m per 10 m of horizontal pipe and 1 m per 3 m of vertical — long lines can drop to 0.4.
What happens if I under-supply trucks?
The pump stops and waits. With ordinary concrete setting in 4-6 hours, a 30-minute wait forces constant reverse pumping and grout addition, and over an hour is effectively a cold joint with reduced strength and watertightness. One spare truck is cheaper than an idle pump: an hour of pump standing time costs far more than an extra load.
How do height and distance affect pump choice?
Every 3 m of lift equals about 1 m of horizontal pressure loss, and 100 m of horizontal pipe loses roughly 10 m of head, plus 3-5 m per bend. Boom pumps are limited by boom length; beyond about 30 storeys or 200 m horizontally you need a trailer pump with a relay. Compute the equivalent pipe length before choosing a pump.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Concrete Pumping Calculator. 2026-10-25. https://jianzhujisuan.com/en/concrete-pump

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.