Earth Pressure Calculator

All three coefficients at once; the gap between active and passive is where the money is.

Also known as lateral earth pressure · rankine earth pressure · Ka Kp K0

Quick answer

With the default inputs: Friction angle φ 30° · Unit weight γ 18 kN/m³ · Wall height or depth 4 m etc.Total thrust per metre 48.0 kN/m

Use your own dimensions ↓

Inputs

°
kN/m³

Result

Total thrust per metre
48.0kN/m
At rest K00.500
Active Ka0.333
Passive Kp3.000
Kp over Ka9.0×
Coefficient used0.333
Pressure at base24.0kPa
Resultant height (from wall base)1.33m
How this is worked out

The three coefficients describe three displacement states and picking the wrong one changes the answer several fold. At rest, K0, applies when the wall does not move at all, such as a basement wall between rigid floors; Jaky gives K0 = 1 - sin phi and it is the conservative no-movement case. Active, Ka, is the wall moving away until the soil shears, tan²(45 - phi/2), the normal design value for retaining walls. Passive, Kp, is the wall pushing into the soil, tan²(45 + phi/2), numerically 1/Ka. At phi 30 degrees Ka is 0.333 and Kp is 3.0, a factor of nine. That is exactly why passive pressure cannot be used freely: it needs wall movement of 2-5% of the height to mobilise, and in an excavation the wall has already deflected before the props go in. Design on something between K0 and Ka, and when you do use Kp, apply a reduction of 0.5 to 0.7 because Rankine over-predicts it.

Next up: Pile Capacity Calculator · Bearing Capacity Calculator

Formula

At restK0 = 1 − sinφ (Jaky)
ActiveKa = tan²(45 − φ/2)
PassiveKp = tan²(45 + φ/2)
Pressure at basep = K·γ·H
Total thrustP = 0.5·K·γ·H²
Resultant heighty = H/3 above base
φ 30°, γ 18 kN/m³, 4 m wall, active case: K0 0.500, Ka 0.333, Kp 3.000, Kp/Ka 9.0, 24 kPa at the base, 48 kN/m total thrust acting 1.33 m above the base.

Friction angle quick reference (γ = 18 kN/m³, 4 m wall, active case, all three coefficients side by side)

Friction angle φ (°)At rest K0Active KaPassive KpKp / KaPressure at base (kPa)Thrust per metre (kN/m)
200.6580.4902.0404.235.370.6
250.5770.4062.4646.129.258.4
300.5000.3333.0009.024.048.0
350.4260.2713.69013.619.539.0
400.3570.2174.59921.115.731.3
450.2930.1725.82834.012.424.7

From φ 20 to 45 degrees, Ka only falls from 0.490 to 0.172, a factor of 2.8, while Kp rises from 2.040 to 5.828, also about 2.9 — because Kp = 1/Ka, so the ratio moves as the square. Quoting the friction angle 5 degrees high therefore cuts the active thrust linearly (25 to 30 degrees takes it from 58.4 to 48.0, an 18% saving) but changes the passive resistance quadratically. Ask the investigation whether the φ given is peak or residual, and drained or undrained: two values for the same layer can differ by 10 degrees.

What groundwater does: dry, total stress and effective stress on the same wall (H = 6 m, water table 2 m down, φ 30 degrees)

CaseSoil pressure at base (kPa)Water pressure (kPa)Total (kPa)vs dry
Dry (unit weight 18 throughout, no water)36.00.036.0—
Below water table, total stress (Ka × saturated unit weight 20)40.0included above40.0+11%
Below water table, effective stress (submerged 10.19 + hydrostatic)25.639.264.8+80%

Multiplying the saturated unit weight by Ka below the water table is the commonest excavation error there is. The soil skeleton carries effective stress and the water carries only hydrostatic pressure, so the two are computed separately. In the example above, effective stress gives 64.8 kPa total against 40.0 kPa for the total-stress shortcut — 38% short, and the shortcut is simply invalid in sand. Cohesive soil may be treated in total stress, but then the total-stress strength parameters (cu, φu) must be used, never effective strength paired with a saturated unit weight. Where there is an aquifer, silty sand, or artesian water under the base, base heave and piping need their own check — this table does not cover them.

Basis

FAQ

How much bigger is passive than active pressure?
Numerically Kp is 1/Ka, so the ratio is 1/Ka² — about 4.2 times at phi 20 degrees, 9 times at 30 and 21 times at 40. The friction angle drives it. That gap has real consequences in an excavation: the retained side is active and the resisting side in front of the toe is passive, so a small movement into the soil mobilises a lot of resistance — provided the movement is acceptable.
How is earth pressure calculated when there is groundwater?
Effective stress: above the water table take the bulk unit weight times Ka; below it take the submerged unit weight (saturated minus 9.81) times Ka; then add the hydrostatic triangle γw·h separately and sum the two. In the H = 6 m, 2 m water table example on this page that gives 64.8 kPa, against 40.0 kPa for multiplying the saturated unit weight by Ka directly. Sand must be done in effective stress; cohesive soil may be done in total stress but then it needs total-stress strength parameters. Never mix the two.
Why can't passive pressure be used directly for anchor capacity?
Because it needs movement. Full passive resistance requires the wall to push 2-5% of its height into the soil — 12 to 30 cm on a 6 m excavation. The wall has moved nothing like that when the anchors are stressed, so a capacity computed from Kp is overstated and the anchor will not hold. Practice applies a reduction of 0.5-0.7 to Kp, or designs on at-rest pressure with a factor of safety. It is in JGJ 120 and most excavation manuals, and it is still the thing most often missed on site.

What to calculate next

These jobs are done back to back on site — follow the steps to work through the whole sequence.

Retaining: pressure to supportStep 1 of 4

  1. 1Earth Pressure Calculator
  2. 2Retaining Wall Stability Calculator
  3. 3Soldier Pile Calculator
  4. 4Ground Anchor Calculator

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Earth Pressure Calculator. 2026-10-25. https://jianzhujisuan.com/en/earth-pressure

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.