Ground Anchor Calculator

Anchor count, length and grout volume - the prestressed upgrade to soil nails.

Also known as ground anchors · tieback anchor · soil anchor

Quick answer

With the default inputs: Wall length 40 m · Number of rows 3 rows · Horizontal spacing 2 m etc.Number of anchors 60 bars

Use your own dimensions ↓

Inputs

rows
Anchor head to bond start, crossing the slip surface
Bond must reach stable ground, normally ≥ 3 m

Result

Number of anchors
60bars
Per row20bars
Length per anchor14.0m
Total length840m
Bond grout volume6.4m³
Strand (3 × Φ15.2)2520m
How this is worked out

An anchor is the prestressed upgrade to a soil nail: nails are grouted full length and work passively, while an anchor is grouted only over its bond, sleeved over the free length and tensioned to prestress the wall. The free length must cross the active slip surface and the bond must reach stable ground with enough pull-out capacity (normally ≥ 3 m, shorter in rock, longer in soft ground). Grout follows the bond hole volume and runs slightly over in porous ground. Strand is estimated as a common 3 × Φ15.2; strand count and prestress follow the design.

Next up: High Strength Bolt Torque Calculator · Plaster and Render Calculator

Formula

Per rown = ⌈length ÷ spacing⌉
TotalN = per row × rows
LengthL = free + bond
GroutV = N × π×(d/2)² × bond length
A 40 m wall, 3 rows at 2 m spacing, 6 m free + 8 m bond, 130 mm holes: 20 per row, 60 total, 14 m each, 840 m total; bond grout 60×π×0.065²×8 ≈ 6.4 m³.

How to work it out

  1. Anchor count = rows × anchors per row, per row = ⌈retention length ÷ horizontal spacing⌉.
  2. The free length must cross the active slip surface into stable ground; bond length is usually at least 3 m (shorter in rock, longer in soft soil).
  3. Total length = free + bond length; grout volume is the bond-hole volume plus an overfill allowance.
  4. Strands are usually 3 × Φ15.2; the number and prestress level follow design, not more-is-better.
  5. Tension in stages, lock off at the design prestress, and protect the anchor head against corrosion.

Where it goes wrong

Material and cost

Anchors are priced per metre (drilling, strand, grouting, tensioning all in), from a few hundred to a thousand-plus each. With long retention and many rows the anchors can out-cost the piles, so lay them out carefully rather than blindly densifying.

On site

Basis

FAQ

What is the difference between an anchor and a soil nail?
The core is active versus passive. A nail bonds full length and only mobilises once the soil moves, so it is passive, deflects more and carries no prestress. An anchor bonds only over its bond, its free length can stretch, and after tensioning it actively holds the wall against the ground - less movement, better control, for displacement-sensitive deep pits and tight neighbours. Anchors have a free length and head anchorage, nails do not, so anchors cost more.
How long should the bond be?
It is back-calculated from the pull-out capacity, not guessed. A longer bond holds more, but the gain tapers because stress is not uniform along it - effective bond runs about 10-20 m in soft ground and only 3-6 m in rock. It must also reach stable ground and pass well beyond the slip surface. Final length comes from pull-out tests and the design capacity; this tool just quantities the length you enter.

What to calculate next

These jobs are done back to back on site — follow the steps to work through the whole sequence.

Retaining: pressure to supportStep 4 of 4

  1. 1Earth Pressure Calculator
  2. 2Retaining Wall Stability Calculator
  3. 3Soldier Pile Calculator
  4. 4Ground Anchor Calculator

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Ground Anchor Calculator. 2026-10-25. https://jianzhujisuan.com/en/ground-anchor