Labour Cost Build-up Calculator
Day rate build-up with overheads, levies and tax.
With the default inputs: Man-days 100 man-days · Day rate 350 CNY · Overhead rate 12% etc.Gross labour cost 44636 CNY
Edit the inputs below to recalculate.Inputs
Result
| Base labour | 35000CNY |
| Overheads | 4200CNY |
| Statutory levy | 1750CNY |
| Pre-tax subtotal | 40950CNY |
| Tax | 3686CNY |
| Gross rate per man-day | 446CNY/man-day |
| Mark-up on base | 27.5% |
| Per 1000 man-days | 44.6410k CNY |
Bases and order of application differ by jurisdiction; this tool uses the simplified route of base labour, then overheads and levies, then tax, which matches most bill-of-quantities practice. Statutory levies cover social insurance, housing fund and environmental charges — they are non-competitive and cannot be discounted. Bundling overhead and levy into one percentage makes negotiation easier.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Base labour | man-days × day rate |
| Overheads | base × overhead rate |
| Levies | base × levy rate |
| Pre-tax | base + overheads + levies |
| Tax | pre-tax × tax rate |
| Gross | pre-tax + tax |
How to work it out
- Establish the man-days first. A man-day is eight hours, and overtime converts at trade convention rather than labour law: four hours of continuous overtime counts as half a man-day.
- Apply the daily rate: 200-260 CNY for general labour, 350-450 for skilled trades (steel fixing, formwork, masonry, plastering), 450-600 for certificated work such as welding and lifting. State whether social insurance is included.
- Basic labour cost B = man-days × daily rate. This is the fee base, and the next three items hang off it — or off labour-plus-material-plus-plant, depending on the contract basis.
- Add overheads M = B × overhead rate, normally 10-15%, covering site management salaries, office costs and travel.
- Add statutory fees L = B × statutory rate, normally 3-6%, covering social insurance, housing fund and environmental levies.
- Pre-tax subtotal P = B + M + L; tax T = P × rate (9% under the general method for construction services, 3% under the simplified method); total including tax = P + T.
Where it goes wrong
- Converting overtime linearly. If eight hours cost 100, two extra hours are not 25 — sites bill in half-days and whole days, and overtime productivity is lower, so linear conversion understates cost.
- Mixing up the base for overheads and statutory fees. Some contracts base them on labour cost, others on labour plus material plus plant; the same 12% can differ threefold. Confirm the base before signing.
- Applying 9% to everything. Labour-only packages, client-supplied materials and legacy projects may qualify for the 3% simplified method. Choosing wrongly costs six percentage points, and the election is locked for 36 months.
- Forgetting social insurance inside statutory fees. With dedicated migrant-worker wage accounts and real-name site management, social insurance and injury cover are mandatory outgoings; omitting them makes the bid non-compliant.
Material and cost
Typical 2024-2025 daily rates: general labour 200-260 CNY, skilled trades 350-450, certificated work 450-600, with tier-one cities 20-30% higher and counties 15% lower. Overheads 10-15%, statutory fees 3-6%, VAT 9% under the general method or 3% simplified.
On site
- Labour is about 20-25% of civil works cost and 35-45% of fit-out. Take the daily rate from the local cost office's published information price rather than estimating it yourself.
- Quota labour rates diverge sharply from market rates — a quota may say 120 CNY/day where the market pays 350 — so pricing labour from quotas badly understates it. Settlement in practice follows market or package rates.
- Labour-only quotations look expensive per unit but exclude material waste and management; add 8-12% for the real all-in cost.
- Rates rise 30-50% around harvest and Chinese New Year. Any programme spanning those windows must carry the increase in the price.
Basis
- Jianbiao [2013] No.44 Composition of construction and installation costs (labour, overheads, statutory fees, tax)
- GB 50500-2013 Code of bills of quantities and valuation for construction works
- Caishui [2016] No.36 Notice on piloting VAT in place of business tax
FAQ
Why is the quoted rate so much higher than the wage?
Can statutory levies be negotiated?
General or simplified tax method?