Lighting Level and Fixture Calculator
Lumen method fixture count, achieved lux and power density.
With the default inputs: Room area 50 m² · Target illuminance 300 lx · Lumens per fixture 3000 lm etc.Fixtures required 9 pcs
Edit the inputs below to recalculate.Inputs
Result
| Calculated (unrounded) | 8.93pcs |
| Total lumens required | 15000lm |
| Effective lumens each | 1680lm |
| Achieved illuminance | 302lx |
| Illuminance margin | 0.8% |
| Total installed power | 270W |
| Power density (LPD) | 5.40W/m² |
| Area per fixture | 5.56m² |
| Spacing in a square grid | 2.36m |
The lumen method suits uniform general lighting and gives average maintained illuminance. Utilisation depends on room index, surface reflectances and luminaire distribution, so exact values come from the manufacturer; the defaults here are for scheme-stage estimates. Power density is a mandatory efficiency metric: offices typically under 9 W/m², retail 10-12, corridors 5.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Fixture count | N = E × A ÷ (Φ × CU × MF) |
| Achieved level | N × Φ × CU × MF ÷ A |
| Power density | N × watts ÷ A |
| Area per fixture | A ÷ N |
| Square spacing | √(A ÷ N) |
| Symbols | E lux, A area, Φ lumens, CU utilisation, MF maintenance |
Illuminance standards and power density limits
| Space | Illuminance lx | Power density W/m² | Note |
|---|---|---|---|
| Corridors and stairs | 100 | 5 | Emergency lighting at least 5 lx |
| Bedroom | 75 | 6 | |
| Kitchen | 100 | 6 | 300 lx at the worktop |
| Office | 300 | 9 | General office work |
| Meeting room | 300 | 9 | |
| Classroom | 300 | 9 | 500 lx on the blackboard |
| Retail floor | 300 | 12 | Good colour rendering needed |
| Fine machining | 500 | — | Set by the process |
| Operating theatre | 750 | — | Theatre lamp separate |
How to work it out
- Set the illuminance target first (GB 50034-2013): 100 lx for a living room, 75 lx bedroom, 150 lx dining, 100 lx kitchen and bathroom; 300 lx for offices and classrooms, 500 lx for drafting rooms. These are maintained values on the working plane, not peaks directly under a fitting.
- Establish the luminous flux per fitting. LED efficacy is 100-140 lm/W, so a 30 W luminaire is nominally 3000-4200 lm — but use the net output after the diffuser, which loses 10-20%.
- Choose the utilisation factor CU: 0.7-0.8 for a light-coloured office, 0.6-0.7 for ordinary finishes, 0.5-0.6 for dark finishes or industrial space. Higher ceilings push it down.
- Choose the maintenance factor MF: 0.8 for clean interiors, 0.7 for general, 0.6 for dusty workshops and kitchens.
- N = E × A ÷ (Φ × CU × MF), rounded up. A 50 m² office at 300 lx with 3000 lm, CU 0.7 and MF 0.8 gives 8.9, so nine fittings.
- Lay them out on a square grid at s = √(A ÷ N) = √(50 ÷ 9) = 2.36 m. The spacing-to-mounting-height ratio should stay between 1.0 and 1.5; beyond that you get visible banding.
Where it goes wrong
- Assuming 1 W of LED equals 100 lm and stopping there. Diffuser loss (10-20%), utilisation and maintenance factors all take a cut, so a design at 300 lx often measures 220 lx once installed.
- Using 0.9 for the utilisation factor. That figure belongs to a white-walled laboratory; a real office ceiling with dark carpet gives 0.6-0.7, and 30% is two or three fittings.
- Checking illuminance but not power density. Meeting the lux target while exceeding the LPD limit fails the energy review — GB 55015 is mandatory.
- Forgetting the maintenance factor. Dust on the diffuser cuts output 20-30% in a year, so a design based on new-lamp output is adequate in year one and short in year two. Users report it as the lights getting dimmer.
Material and cost
30 W LED panels run 60-150 CNY each at project pricing, downlights 40-100, high-bay fittings 150-400, magnetic track heads 200-500. Installation labour is 15-30 CNY per fitting. Designing in 10% spare fittings is much cheaper than retrofitting, which means re-cutting ceilings and re-running cable.
On site
- In workshops and warehouses above 4 m, use narrow-beam fittings or reflectors. Wide distribution just washes the walls and never reaches the working plane.
- In classrooms and reading rooms, run luminaire axes perpendicular to the blackboard or shelving to avoid shadows and veiling reflections.
- Flicker and glare generate more complaints than illuminance levels. Keep UGR below 19 in offices and 22 in industrial space, using louvers or anti-glare shields.
- Measure illuminance at night with no daylight. Daytime readings are mostly sunlight and tell you nothing.
Basis
- GB 50034-2013 Standard for lighting design of buildings, illuminance values and lighting power density limits
- GB 55015-2021 General code for energy efficiency and renewable energy utilisation in buildings
- GB/T 5700-2008 Measurement methods for lighting
FAQ
Why does the measured level fall short of design?
Is more light always better?
How is power density controlled?