Pile Capacity Calculator
N value for sand, cu for clay: shaft and base worked separately, then divided by a factor of safety.
Also known as pile load capacity · pile bearing capacity · driven pile capacity
With the default inputs: Pile diameter 0.6 m · Pile length 20 m · Soil type Sand etc.Allowable capacity 1508 kN
Use your own dimensions ↓Inputs
Result
| Perimeter | 1.885m |
| Base area | 0.2827m² |
| Unit shaft friction | 40.0kPa |
| Shaft capacity | 1508kN |
| Unit end bearing | 8000kPa |
| Base capacity | 2262kN |
| Ultimate capacity | 3770kN |
| Base share of total | 60% |
| Method | SPT (Meyerhof) |
How this is worked out
Shaft and base resistance are computed separately because they mobilise at very different settlements: shaft friction peaks at roughly 0.5% of the diameter, end bearing needs 5-10% of the diameter to fully develop. Adding ultimate values and dividing once is therefore optimistic — practice applies a larger factor to the base or caps the unit end bearing. The SPT route uses fs = 2N kPa and qb = 400N kPa (Meyerhof); the clay route uses the alpha method with fs = alpha x cu (alpha typically 0.5) and qb = 9cu. These are preliminary correlations that scatter by about 30%, so a real design needs a static load test or dynamic testing. Correct N to N60 and to an effective overburden of 100 kPa before using it — uncorrected blow counts in loose saturated sand under-read and under-predict capacity. For pile groups, apply a group efficiency reduction below 3D spacing.
Next up: Bearing Capacity Calculator · Retaining Wall Stability Calculator
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Perimeter | u = π·D |
| Base area | Ab = π·D²/4 |
| Shaft, sand | fs = 2N (kPa, cap 100) |
| Base, sand | qb = 400N (kPa, cap 15000) |
| Shaft, clay | fs = 0.5·cu |
| Base, clay | qb = 9·cu |
| Ultimate | Qu = fs·u·L + qb·Ab |
| Allowable | Qa = Qu / FS |
Basis
- JGJ 94-2008, §5.3 — single pile vertical capacity by the static formula
- JGJ 94-2008, Table 5.3.5 — shaft and end resistance parameters
- JGJ 94-2008, §5.8 — settlement of the pile group
FAQ
How do I calculate the capacity of a single pile?
Is a 60% base share realistic?
What to calculate next
These jobs are done back to back on site — follow the steps to work through the whole sequence.
Foundations: when bearing capacity is not enoughStep 2 of 4
- 1Bearing Capacity Calculator
- 2Pile Capacity Calculator
- 3Pile Cap Calculator
- 4Bored Pile Concrete and Rebar Calculator
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Pile Capacity Calculator. 2026-10-25. https://jianzhujisuan.com/en/pile-capacity