Advance recovery, retention and the amount due this period.

Quick answer

With the default inputs: Contract sum 1000000 CNY · Value this period 200000 CNY · Cumulative before this period 400000 CNY etc.Amount due this period 154000 CNY

Edit the inputs below to recalculate.

Inputs

CNY
CNY
CNY
%
%
Recovery begins at this share of the contract sum
%

Result

Amount due this period
154000CNY
Total advance200000CNY
Recovery threshold300000CNY
Cumulative including this period600000CNY
Advance recovered to date20000CNY
Recoverable by now60000CNY
Recovered this period40000CNY
Retention this period6000CNY
Value this period200000CNY
Cumulative share of contract60.0%

The recovery threshold means that once cumulative value reaches a set share of the contract sum, the client starts recovering the advance each period at the advance percentage. Retention is usually 3% of each period value, capped at 3% of the contract sum, released after the defects liability period. Note retention is calculated on the period value, not on the amount due — the difference matters.

Formula

Advancecontract × advance %
Thresholdcontract × recovery start %
Recoverable(cumulative − threshold) × advance %
This periodrecoverable now − recoverable before
Retentionperiod value × retention %
Amount dueperiod value − recovery − retention
A 1 million contract with 200,000 this period and 400,000 before, 20% advance, 30% threshold and 3% retention: 200,000 advance, 300,000 threshold, 40,000 recovered, 6,000 retention — 154,000 due.

How to work it out

  1. Line up the three figures first — contract value, value completed this period and cumulative value before this period — on the same basis: all inclusive or all exclusive of tax, and whether variations are included.
  2. Advance total A = contract value × advance percentage, typically 10-30% and covering material stocking.
  3. Set the recovery start point P = contract value × start percentage, typically 20-40%. Conceptually it is the moment when the value of materials still needed equals the advance.
  4. Cumulative recovery R = (cumulative value completed − start point) × advance percentage. Nothing is recovered until cumulative completion passes the start point.
  5. Recovery this period = cumulative recovery now − cumulative recovery last period. The difference method handles period boundaries automatically without double counting or omission.
  6. Retention Q = value this period × retention rate (typically 3-5%); payment due = value this period − recovery this period − retention.

Where it goes wrong

Material and cost

Market practice: advance 10-30% (government projects often 10-20% including material stocking), recovery start point 20-40%, retention 3-5% (3% common in building, 5% in municipal), progress payment ratio 70-85% on monthly measurement. Retention is released after one to two years, and since 2017 bank guarantees may replace cash — a significant cash-flow release.

On site

Basis

FAQ

Why set the recovery threshold at 30%?
Because the advance exists to mobilise: buying materials and bringing in plant. By the time 30% of value is certified, materials have turned into work and progress payments sustain the site, so recovery no longer starves it. A lower threshold squeezes the contractor sooner; too high and the client carries more risk of misuse.
Can retention be replaced by a bond?
Yes, and more projects do. Rules on clearing construction deposits state that a bank guarantee or insurance policy may replace cash retention and the client must not refuse. A bond frees 3% of cash flow for a fee of roughly 1-2% a year, and it is worth writing into the contract.
What if the client delays payment?
Check the contractual payment period, typically 28-56 days; late payment carries interest at the market loan rate. Construction price priority rights protect the contractor, but the window is 18 months from completion and lapses after that. In practice the decisive thing is complete measurement and sign-off records — without them, a good case goes nowhere.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Progress Payment Calculator. 2026-10-25. https://jianzhujisuan.com/en/progress-payment

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.