Rebar Cost Calculator
Material, fabrication, fixing and the all-in cost per tonne.
With the default inputs: Rebar tonnage 100 · Rebar price 4200 CNY/t · Fabrication 350 CNY/t etc.Total rebar cost 55.10 10k CNY
Edit the inputs below to recalculate.Inputs
Result
| Tonnage with waste | 103.00t |
| Material | 43.2610k CNY |
| Fabrication | 3.6010k CNY |
| Fixing labour | 8.2410k CNY |
| All-in per tonne | 5350CNY/t |
| Material share | 78.5% |
| Labour and fabrication share | 21.5% |
| Cost of waste | 1.6010k CNY |
| All-in per 100 t | 53.5010k CNY |
Rebar is the most volatile major material, with 500 per tonne swings within a month, so quotes need a price adjustment clause — usually tied to the published average for the size, adjusted beyond ±5%. Site fabrication wastes 3-5%, while factory-cut and bent bar cuts that to 1-2%, and the saved steel often pays the delivery premium.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Tonnage with waste | total × (1 + waste%) |
| Material | tonnage × price |
| Fabrication | tonnage × rate |
| Labour | tonnage × fixing rate |
| Total | material + fabrication + labour |
| All-in per tonne | total ÷ tonnage |
How to work it out
- Break the total tonnage down by bar size and grade (HRB400 by diameter) first. Unit price and fabrication cost differ by size, and averaging across them distorts the result.
- Compute the quantity including waste: Q = tonnage × (1 + waste). Waste covers offcuts, lap lengths and accessory bars such as spacers and ladder bars — normally 3-5%, at the top of the range for complex geometry.
- Material cost = Q × unit price. HRB400 rebar commonly runs 3800-4500 CNY/t, with coiled and wire rod slightly higher and plain round bar slightly lower.
- Fabrication = Q × fabrication rate, typically 300-450 CNY/t covering straightening, cutting, bending and thread cutting for couplers.
- Fixing labour = Q × fixing rate, typically 700-1000 CNY/t, at the top of the range for basements and congested joints.
- Total = material + fabrication + labour; the all-in rate per tonne is that total divided by Q, which is the figure to compare against subcontract quotations.
Where it goes wrong
- Allowing 2% waste. Accessory bars — spacers, ladder bars, positioners — are often outside the drawn quantity and add 2-4% on their own, before offcuts. Three percent is a floor, not a ceiling.
- Comparing material price only. A 100 CNY/t difference in material is trivial next to fabrication ranging 300-450 and labour 700-1000; those two drive most of the spread between quotes.
- Estimating tonnage from floor area times a steel-content index and settling on it. Indices (45-65 kg/m² for residential, 100-150 for basements) are for feasibility only; settlement must follow bar schedules.
- Ignoring stock lengths and laps. With 9 m stock, column and beam main bars inevitably lap at 35d-40d per the code, and that steel is routinely missing from budgets.
Material and cost
HRB400 rebar runs 3800-4500 CNY/t and moves with futures — 500 CNY swings between quarters are common. Fabrication 300-450 CNY/t, fixing labour 700-1000. The all-in rate typically lands at 5000-6000 CNY/t. Formwork, concrete and plant are separate.
On site
- With steel this volatile, large projects often use a price-linkage clause tied to the published mill price on the order date. Fix the reference date and the adjustment formula at contract stage.
- Check whether the fabrication rate includes couplers and thread rolling. Mechanical couplers save steel against lapping but cost more to fabricate, so cost each joint type separately.
- Scrap recovery offsets part of the cost, and good bar-schedule optimisation typically saves 1-2% of steel — more effective than haggling on price.
- Any substitution on site, larger for smaller or equal-grade swap, needs design approval. Equal strength is not enough: anchorage, crack control and seismic detailing all have to be checked.
Basis
- GB 50500-2013 Code of bills of quantities and valuation for construction works, reinforcement works
- GB 50010-2010 (2015 edition) Code for design of concrete structures, detailing provisions
- GB 50666-2011 Code for construction of concrete structures, reinforcement works
FAQ
Why does fixing cost so much more than fabrication?
Is factory-cut bar actually cheaper?
How do you fix the rebar price?