Scaffolding Cost Calculator
Rent by duration plus erection labour, giving total cost.
With the default inputs: Scaffold area 1000 m² · Duration 90 days · Monthly rent 18 CNY/m² etc.Total scaffold cost 80000 CNY
Edit the inputs below to recalculate.Inputs
Result
| Duration in months | 3.00months |
| Rent | 54000CNY |
| Erection labour | 22000CNY |
| Material loss | 4000CNY |
| Cost per m² | 80.00CNY/m² |
| Cost per m² per day | 0.889CNY/m²·day |
| Rent share | 67.5% |
| Cost of 30 extra days | 18000CNY |
| Rent per day | 600CNY/day |
Scaffold cost is highly duration-sensitive: stretching the hire from three months to five raises rent by 67% while erection cost stays put. The aim is to shorten occupation, not to squeeze the rate. Also pin down the free period — most hirers allow 15-30 days before daily charges start, and that clause is worth negotiating.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Duration | days ÷ 30 |
| Rent | area × monthly rate × months |
| Labour | area × erection rate |
| Loss | area × loss rate |
| Total | rent + labour + loss |
| Cost per m² | total ÷ area |
How to work it out
- Establish the system and the pricing basis first: tube-and-coupler is hired by area per month, ringlock and climbing systems are usually hire plus erection, and ground-supported scaffolding is often a lump sum per area.
- Convert the hire period to months: days ÷ 30. The clock runs from mobilisation to final strike and demobilisation, not from first use to last use — idle periods are billed.
- Hire cost R = scaffold area × monthly rate × months. Tube-and-coupler runs 15-25 CNY/m² per month; ringlock is slightly higher.
- Erection and striking labour = area × rate (20-30 CNY/m²). Above 24 m the price rises because the scaffold must be staged and offloaded in lifts.
- Material loss = area × loss rate (3-6 CNY/m²), covering lost couplers and bent or deformed tubes that must be paid for.
- Total = hire + labour + loss; the rate per square metre is that total divided by area, which is the figure to compare against a scaffolding subcontract quote.
Where it goes wrong
- Computing the hire period from actual working days. Contracts run from mobilisation to demobilisation, so programme slippage, inspection waits and striking scheduling all accrue hire — typically 30-50% more than planned.
- Using floor area as scaffold area. External scaffold area is the external wall perimeter times the scaffold height, roughly 0.8-1.2 times floor area for housing but a completely different ratio for factories and wide-span buildings.
- Omitting the height premium. Ground-supported scaffold above 24 m needs offloading and staging with more labour and material; above about 50 m it is generally not permitted and must become climbing or cantilevered.
- Leaving out safety netting, toe boards, decking and wall ties. These accessories are 10-15% of scaffold cost and quotes often cover only tubes and couplers.
Material and cost
Tube-and-coupler hire is 15-25 CNY/m² per month, erection and striking 20-30 CNY/m², material loss 3-6 CNY/m². Ringlock hires at 20-30 but erects faster with 20% less labour. Climbing formwork needs 200-350 CNY/m² upfront but can be reused across projects, making it cheaper overall above about 30 storeys.
On site
- Hire duration is the least controllable element. Fix a minimum period and an extension rate in the contract, or a slipped programme will cost more in hire than the erection itself.
- Ringlock costs more per month but erects two to three times faster, and the labour saving usually exceeds the hire premium — the right choice when the programme is tight.
- Coordinate the scaffold design with tower crane and hoist positions. Every relocation is a separate charge.
- Provide safety and debris netting to local requirements; many regions mandate flame-retardant mesh at about 1.5 times the price of standard netting.
Basis
- JGJ 130-2011 Technical code for safety of steel tubular scaffold with couplers in construction
- JGJ 231-2010 Technical specification for safety of socket-type ringlock steel tubular scaffold
- GB 50500-2013 Code of bills of quantities and valuation for construction works, preliminaries
FAQ
Why is scaffolding priced by area, not weight?
Rent or buy?
How much does delay cost on scaffolding?