Tower Crane Foundation Check
Base pressure, eccentricity and overturning ratio in one pass.
With the default inputs: Vertical load Fv 500 kN · Horizontal load Fh 30 kN · Overturning moment M 1200 kN·m etc.Maximum base pressure 85.2 kPa
Edit the inputs below to recalculate.Inputs
Result
| Foundation self-weight | 1260.0kN |
| Soil surcharge | 64.8kN |
| Total vertical load | 1824.8kN |
| Moment at base | 1242.0kN·m |
| Average pressure | 50.7kPa |
| Eccentricity e | 0.681m |
| Allowable e = B ÷ 6 | 1.000m |
| Maximum pressure | 85.2kPa |
| Minimum pressure | 16.2kPa |
| Capacity limit 1.2 fak | 216kPa |
| Overturning factor | 4.41 |
| Concrete volume | 50.40m³ |
Both checks are mandatory. Bearing: pMax = N/A × (1 + 6e/B) must not exceed 1.2 fak, and eccentricity must stay within B/6 — beyond that the base goes into zero pressure (lifting off), the formula no longer applies and the pad must be enlarged. Overturning: K = N × B/2 ÷ M, normally at least 1.5. Remember to add the horizontal force couple Fh × h to the moment at the base; it is often forgotten. Assumes a square pad, uniform ground and catalogue maximum loads — an initial sizing only. The formal design must be a sealed calculation by a qualified engineer to the crane manual, the ground investigation and the tower crane foundation code.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Self-weight | G = 25 × side² × depth |
| Soil surcharge | Gs = side² × (embedment − depth) × 18 |
| Total vertical load | N = Fv + G + Gs |
| Moment at base | Mk = M + Fh × depth |
| Eccentricity | e = Mk ÷ N, require e ≤ B ÷ 6 |
| Maximum pressure | pMax = N ÷ A × (1 + 6e ÷ B) |
| Overturning factor | K = N × B ÷ 2 ÷ Mk, require K ≥ 1.5 |
How to work it out
- Average bearing pressure p = (Fv + G) / A, where G is the base self-weight (volume × 25 kN/m³) and A the base area.
- Eccentricity e = M / (Fv + G), with M the overturning moment including the horizontal force times base depth.
- Check eccentricity against B/6 (B being the base side). Beyond B/6 the base lifts and part of the foundation separates from the ground.
- Peak pressure pMax = (Fv + G)/A × (1 + 6e/B) must not exceed 1.2 × fak, the allowable bearing pressure after depth and width correction.
- Overturning factor K = (Fv + G) × B / (2 × M) must be at least 1.5 — the last line of defence for a tower crane.
Where it goes wrong
- Checking average pressure only — a crane's overturning moment dwarfs its vertical load, so the average passes while the edge pressure exceeds 1.2fak by more than double.
- Omitting or miscomputing base self-weight — a 6 × 6 × 1.4 m concrete base weighs 504 kN, comparable to the 500 kN crane load; leaving it out grossly inflates the eccentricity.
- No depth correction on fak — at 1.5 m embedment the allowable pressure must be corrected for depth; skipping it is either wasteful or unsafe depending on which way you err.
- Taking the overturning factor as 1.0 — the code requires 1.5 (1.15 in some cases); 1.0 means no reserve at all and is a serious hazard.
Material and cost
A 6 × 6 × 1.4 m C35 base of about 50 m³ costs 40000-80000 CNY including steel, formwork and excavation. Piling on soft ground adds 100000-250000. Crane hire 15000-40000 CNY per month by model.
On site
- Concrete must reach 80% of design strength before erection, evidenced by companion-cured cubes.
- Provide drainage; standing water lowers bearing capacity and is a common precursor to crane overturning.
- Erection, climbing and dismantling are all major hazard operations needing expert review and a licensed erector.
Basis
- GB/T 13752-2017 Design rules for tower cranes
- JGJ 33-2012 Technical code for safe use of construction machinery
- GB 50202-2018 Code for acceptance of foundation construction, Chapter 5
FAQ
Why must eccentricity stay within B/6?
Why is the horizontal-force moment so easily missed?
What if the checks fail?