Water Demand Calculator
Peak day and peak hour demand, with pipe and tank sizing.
With the default inputs: Occupancy 100 persons · Use per person 50 L/person·day · Hourly peaking factor 2.5 etc.Peak day demand 5.00 m³/d
Edit the inputs below to recalculate.Inputs
Result
| Average hourly | 0.625m³/h |
| Peak hourly | 1.563m³/h |
| Peak flow | 0.434L/s |
| Calculated bore | 21.5mm |
| Suggested DN | 25mm |
| Actual velocity | 0.88m/s |
| Tank at 30% of peak day | 1.50m³ |
| Annual demand | 1825m³ |
| Per person per day | 50L |
The hourly factor is peak over average hourly flow, and the smaller the population the larger it gets — up to 4-5 below ten people, because use concentrates. This covers domestic use only, excluding fire, irrigation and unaccounted water, usually another 10-15%. Potable tanks are sized at 20-30% of the peak day; fire storage is calculated separately to code.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Peak day | occupancy × per-capita ÷ 1000 |
| Average hourly | peak day ÷ operating hours |
| Peak hourly | average hourly × Kh |
| Peak flow | peak hourly × 1000 ÷ 3600 |
| Pipe bore | √(4q ÷ (π × v)) |
| Tank volume | peak day × 20-30% |
Reference water use by building type
| Building type | Unit | Allowance | Hourly factor |
|---|---|---|---|
| Dwelling with shower | L/person·day | 130-200 | 2.0-2.5 |
| Dwelling without shower | L/person·day | 80-120 | 2.0-2.5 |
| Office | L/person·shift | 30-50 | 1.5-2.0 |
| Dormitory | L/person·day | 80-100 | 2.5-3.0 |
| Hotel room | L/bed·day | 250-400 | 2.0-2.5 |
| Restaurant | L/person·meal | 15-20 | 1.5-2.0 |
| Teaching building | L/person·day | 30-50 | 1.5-2.0 |
| Hospital ward | L/bed·day | 400-600 | 2.5-3.0 |
How to work it out
- Set the demand figure (GB 50015-2019): 130-300 L per person per day for dwellings with central hot water, 100-200 without; 30-50 L per person per shift for offices; 100-150 for dormitories; 20-25 per meal for canteens. Base it on actual occupancy, not on beds or desks.
- Peak-day volume Qd = occupancy × demand ÷ 1000, in m³/day.
- Average hourly Qh = Qd ÷ operating hours; peak hourly Qh,max = Qh × hourly peaking factor Kh (2.0-2.5 for dwellings, 1.5-2.0 for offices).
- Peak flow q = Qh,max × 1000 ÷ 3600, in L/s. Two unit conversions happen here, which is where orders of magnitude go wrong.
- Bore d = √(4q ÷ (π × v)) with v at 1.0-1.5 m/s for domestic supply, at the low end for small bores.
- Tank volume V = Qd × 20-30%. Where the pumps cannot run continuously or mains pressure swings widely, size on the peak shift instead of defaulting to 20%.
Where it goes wrong
- Sizing the pipe on average hourly flow. At the morning peak every tap runs at once, and the instantaneous flow is 2.5 times the average — a pipe sized on the average collapses in pressure.
- Basing occupancy on beds or workstations. Offices typically run at 80% of desk count, while outpatient clinics and schools run over. Judge by how the building is actually used.
- Making the tank hold a full peak day. The tank then takes half the roof, and water resident for more than 48 hours loses chlorine residual and degrades in quality.
- Sharing one tank between domestic supply and fire reserve. Fire pumps draw the domestic reserve down with them; the codes require the two to be effectively separated.
Material and cost
Stainless domestic tanks cost 1000-1800 CNY/m³ including insulation and base. Variable-speed booster sets run 30,000-80,000 CNY for 10-30 m³/h. Upsizing the pipe one step adds 30-50% to PPR material, which is trivial next to the cost of complaints and rework over poor pressure.
On site
- The service pipe into a dwelling is the most overlooked item. A 100 m² three-bedroom flat peaks around 0.2 L/s, so DN20 is nominally enough — but with two showers and a washing machine filling, DN20 drops noticeably. Specify DN25.
- Do not confuse the hourly peaking factor Kh with the daily factor Kd. Kd governs source and treatment works; Kh governs the network and pipe sizing.
- Roof tanks need level control and an overflow pipe discharging indirectly through an air gap. Connecting the overflow straight to a drain is a contamination risk.
- When an old estate has poor pressure, check the service pipe size, meter bore and whether valves are half shut before adding a pump. Local blockage explains a surprising number of cases.
Basis
- GB 50015-2019 Standard for design of building water supply and drainage, water supply and demand figures
- GB 50555-2010 Standard for water conservation design of civil buildings
- GB 5749-2022 Standards for drinking water quality
FAQ
Why do per-capita figures vary so much by building type?
How is the hourly peaking factor set?
How is tank volume determined?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Water Demand Calculator. 2026-10-25. https://jianzhujisuan.com/en/water-demand