Bolt Capacity Calculator

§ Code basis: EN 1993-1-8 (Europe / Commonwealth) — The design equations differ, so the values are not interchangeable - recalculate with your own code.

Shear or bearing, whichever is lower, governs — above 9 mm plate it is usually shear.

Also known as bolt shear capacity · bolt bearing capacity · bolt strength

Quick answer

With the default inputs: Bolt diameter d 20 mm · Bolt grade Grade 8.8 · Bolt tensile strength fub 800 MPa etc.Design resistance per bolt 94.0 kN

Use your own dimensions ↓

Inputs

MPa
MPa

Result

Design resistance per bolt
94.0kN
Tensile stress area As (threads)244.8mm²
Gross area A (shank)314.2mm²
Coarse pitch P2.50mm
Shear factor αv0.60
Shear planes1faces
Shear resistance per plane94.0kN
Shear resistance (1 planes)94.0kN
Hole diameter d022.0mm
Bearing factor αb0.606
Bearing resistance (single plate t)104.2kN
Governing modeShear controls
Group total564kN
Min edge 1.5d033mm
Min pitch 2.5d055mm
How this is worked out

Always compute both and take the lower. Shear checks the bolt itself, 0.6 fub A / 1.25; double shear multiplies the bolt resistance by two but does not multiply bearing — a bolt through three plates works on two shear planes, yet each plate still bears separately, so bearing is taken on the thinner plate. A double-shear joint therefore often flips from shear-controlled to bearing-controlled, and checking a single plane or shear alone overstates the connection. bearing checks the plate, 2.5 ab fu d t / 1.25. The bearing factor ab is the smallest of three ratios — edge e/(3d0), pitch p/(3d0) minus 0.25, and strength fub/fu — capped at 1.0. The usual mistake is checking shear only, and using the gross area: an M20 grade 8.8 looks generous at 120 kN on the gross section, but the threaded stress area gives 94 kN, 28% less. Against a 10 mm S355 plate at 40 mm edge the bearing value is 104 kN, so shear governs here; bearing only takes over below about 9 mm plate. Thin plates and short edge distances lose on bearing, so the fix is more bolts, not bigger ones. Several things here do not show up as a reduced capacity but will tear the connection apart: edge distance below 1.5d0 causes tear-out; pitch below 2.5d0 allows block shear along a row; in a long joint (end bolts more than 15d apart) the shear resistance must be multiplied by beta_Lf = 1 - (Lj - 15d)/(200d), floored at 0.75, because the load does not distribute evenly and the end bolts carry more; and an eccentrically loaded group must be split by polar moment of inertia rather than equally. This tool takes the smallest of the three ab ratios, which applies the worst bolt to all of them and is conservative: strictly the end row uses e1/3d0 and inner rows use p1/3d0 - 0.25, and k1 = 2.5 assumes the transverse edge distance is at least 1.5d0, below which k1 = 2.8e2/d0 - 1.7 governs. These are design values with the 1.25 material factor already applied, so do not compare them with tested failure loads.

Next up: Wind Load Calculator · Snow Load Calculator

Formula

Shear area (threads)As = π/4·(d − 0.9382P)² M20 P=2.5 → 245 mm²
Shear resistanceFv,Rd = αv·fub·A/γM2
αv (grades 4.6, 8.8)0.6
αv (grade 10.9)0.5
Bearing factorαb = min(e/3d0, p/3d0 − 0.25, fub/fu, 1.0)
Bearing resistanceFb,Rd = 2.5·αb·fu·d·t/γM2
GroupN = min(Fv,Rd, Fb,Rd) × n
M20 grade 8.8 at fub 800, plate fu 430, 10 mm thick, 40 mm edge, 60 mm pitch, single shear, six bolts: stress area 245 mm², 94.1 kN in shear, 22 mm hole, αb 0.606, 104.2 kN bearing — shear governs, 94.1 kN per bolt and 565 kN for the group.

Basis

The codes below are listed for comparison. This calculator returns EN 1993-1-8 values only.

FAQ

How much load can one bolt take?
Check shear and bearing and take the lower. An M20 grade 8.8 in single shear gives 94 kN in shear using the threaded stress area of 245 mm², not the gross 314; against a 10 mm plate with 40 mm edge distance bearing is 104 kN, so 94 kN is the working figure. Above about 9 mm plate shear governs; only thin plates crush the hole first. Using the gross area for shear is the classic error and overstates by 28%.
What is the difference between high strength and ordinary bolts?
It is the load path, not the steel. Ordinary bolts transfer load through the shank in shear and the hole in bearing, and the joint slips before it works. Friction grip high strength bolts are pre-tensioned so the plates are clamped and load crosses by friction — no slip, better fatigue, but they need a torque wrench and a final tightening check. This tool computes the shear and bearing (bearing type) case; the friction grip resistance is mu n 0.7 fub A / 1.25, with mu about 0.5 for grit blasted and 0.3 for painted surfaces, usually lower than bearing type — you trade capacity for no slip. Use friction grip wherever the load reverses or fatigues.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Bolt Capacity Calculator. 2026-10-25. https://jianzhujisuan.com/en/bolt-capacity

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.