Punching Shear Calculator

§ Code basis: EN 1992-1-1 (Europe / Commonwealth) — The design equations differ, so the values are not interchangeable - recalculate with your own code.

A column punching through a slab is a race between the perimeter ring and the load.

Also known as punching shear check · slab punching · column punching shear

Quick answer

With the default inputs: Column width a 400 mm · Column depth b 400 mm · Effective depth d 200 mm etc.Punching resistance 613 kN

Use your own dimensions ↓

Inputs

MPa
%
kN

Result

Punching resistance
613kN
Size effect k2.000
Reinforcement ratio1.00%
Punching stress vRd,c0.746MPa
Minimum vmin0.542MPa
GoverningvRd,c
Critical perimeter u14113mm
Failure surface area0.823m²
Resistance613kN
Utilisation82%
Shear reinforcement neededNot required
Perimeter offset from face400mm
How this is worked out

Punching is the column pushing through the slab. The failure surface is a cone starting 2d out from the column face, so the critical perimeter is u1 = 2(a + b) + 4πd for a rectangular column — not the column perimeter, and not 4(a + b + 2d). The resistance is vRd,c = 0.12 k (100 rho fck)^(1/3), where k handles the size effect (thicker slabs have lower unit strength, falling from a cap of 2.0, which a 200 mm slab just reaches), rho is the tension reinforcement ratio capped at 2%, and fck is concrete strength, which enters as a cube root. There is also a floor: vRd,c must not be taken below vmin = 0.035 k^1.5 sqrt(fck). At very low reinforcement the expression falls under that, vmin governs, and skipping the check under-predicts capacity by about a fifth. A point often missed: without shear reinforcement, going from C30 to C50 raises the resistance only about 18% because of that cube root. To gain real capacity, increase the slab depth or add a drop panel or links. Above 100% utilisation, shear reinforcement is mandatory, the resistance becomes 0.75 vRd,c u1 d plus the contribution of the links, and the check must be repeated on a perimeter at 1.5d — adding links without rechecking the outer ring just moves the failure outside them. Flat slabs also carry unbalanced moment from the column, and edge and corner columns are the critical cases.

Next up: Wind Load Calculator · Snow Load Calculator

Formula

Size effectk = 1 + √(200/d) ≤ 2.0
Punching stressvRd,c = 0.12·k·(100ρ·fck)^(1/3) (MPa)
Minimumvmin = 0.035·k^1.5·√fck; use max(vRd,c, vmin)
Critical perimeteru1 = 2(a + b) + 4πd
ResistanceVRd,c = vRd,c·u1·d
Utilisationη = N / VRd,c
With linksVRd,cs = 0.75·vRd,c·u1·d + 1.5(d/sr)·Asw·fywd
400×400 mm column, 200 mm effective depth, C30, 1.0% reinforcement, 500 kN reaction: k 2.0, vRd,c 0.746 MPa, critical perimeter 4113 mm, 613 kN resistance, 82% utilisation and no shear reinforcement required.

Basis

The codes below are listed for comparison. This calculator returns EN 1992-1-1 values only.

FAQ

How do I check punching shear?
Three steps. Work out the critical perimeter, u1 = 2(a + b) + 4πd, located 2d from the column face. Work out the punching stress, vRd,c = 0.12 k (100 rho fck)^(1/3) with k = 1 + √(200/d) capped at 2.0. Multiply for the resistance, VRd,c, and compare with the column reaction. A 400×400 column with d 200, C30 and 1% steel gives u1 4113 mm, 0.746 MPa and 613 kN; a 500 kN reaction is 82% utilised and fine. Above 613 kN you need links or a drop panel.
Is it better to thicken the slab or raise the concrete grade?
Thicken the slab. Depth appears three times — in the size factor k, inside the perimeter u1 and again as a multiplier — but k = 1 + sqrt(200/d) falls as d grows and cancels part of it, so the real exponent is about 1.5 to 1.8 rather than 3. On this 400×400 column at C30 and 1% steel, going from d 200 to 240, 20% more depth, lifts capacity from 613 to 790 kN, roughly 29% rather than 40%. Concrete strength only enters as a cube root: C30 to C50 is 19%. On cost, extra depth is a small concrete increment while two grades up is a real price step per cubic metre, so adjust thickness first, then a local drop panel, and only then shear links, which are expensive to place and easy to omit.

What to calculate next

These jobs are done back to back on site — follow the steps to work through the whole sequence.

Structure: loads before membersStep 4 of 4

  1. 1Wind Load Calculator
  2. 2Snow Load Calculator
  3. 3Seismic Base Shear Calculator
  4. 4Punching Shear Calculator

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Punching Shear Calculator. 2026-10-25. https://jianzhujisuan.com/en/punching-shear

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.