算BuildCalc

Drainage Pipe Slope Calculator

Standard slope by diameter, fall over the run and velocity check.

Quick answer

With the default inputs: Nominal diameter DN110 · Pipe length 20 · Actual slope 2.0%Fall over the run 0.400 m

Edit the inputs below to recalculate.
Pipe length mNominal diameterActual slope %
Slope depends on size: 25‰ at DN50, 12‰ at DN100, 7‰ at DN150. It is fall divided by length, not an angle.

Inputs

%
Not less than standard, and not excessive

Result

Fall over the run
0.400m
Diameter110mm
Actual slope2.00%
Standard slope2.0%
Slope checkAdequate
Fall per metre20.0mm
Full-bore velocity0.99m/s
Self-cleansingAdequate
Level difference0.400m
Fall at standard slope0.400m

Velocity uses Manning, v = (1/n)·R^(2/3)·i^(1/2), with n = 0.013 for plastic and full-bore flow. Self-cleansing needs at least 0.6 m/s or solids settle; above 5 m/s the pipe erodes. Steeper is not better — fast water outruns the solids and leaves them behind, which is especially marked on branch runs.

Formula

Falllength × slope
Slopefall ÷ length as a decimal
Velocity(1/n) × R^(2/3) × i^(1/2)
Hydraulic radiusd ÷ 4 for a full circular pipe
Self-cleansingv ≥ 0.6 m/s
Standard slopes2% at DN110, 1% at DN160
DN110 over 20 m at 2%: a 0.400 m fall, 20 mm per metre and 0.99 m/s full-bore — self-cleansing. Drop to 1% and velocity falls to 0.70 m/s, where solids settle over time.

Standard and minimum drainage slopes

DNStandard slopeMinimum slopeFall per 10 m at standardFall per 10 m at minimum
DN503.5%2.5%350250
DN752.5%1.5%250150
DN1102.0%1.2%200120
DN1601.0%0.7%10070
DN2000.8%0.5%8050
DN3150.5%0.3%5030

How to work it out

  1. Look up the standard slope for the bore (GB 50015-2019): 3.5% at DN50, 2.5% at DN75, 2.0% at DN110, 1.0% at DN160, 0.8% at DN200, 0.5% at DN315. Larger pipes tolerate flatter falls.
  2. Work out the fall h = length × slope. A 20 m DN110 run at 2% needs 0.4 m, which has to be found in the ceiling void before installation, not discovered during it.
  3. Check velocity: v = (1/n) × R^(2/3) × i^(1/2), with n about 0.009 for plastic and hydraulic radius R = d÷4 for a full pipe.
  4. Self-cleansing requires v ≥ 0.6 m/s, below which solids settle and block. Excess velocity scours the wall and is noisy, so there is an upper limit too.
  5. If the fall is unavailable there are two routes: raise the start point (costing ceiling or floor level) or use a larger bore, which permits a flatter slope. Changing the pipe size is usually cheaper than changing levels.

Where it goes wrong

Material and cost

PVC-U drainage pipe runs 12-20 CNY/m at DN110 and 25-40 at DN160, fittings extra. Insufficient fall means raising the whole bathroom floor or lowering the ceiling, which costs many times the price of the pipe — the most expensive mistake in drainage.

On site

Basis

FAQ

Why is a steeper drain worse?
Because fast water outruns the solids. On a steep run the flow is swift but shallow, so solids roll along the invert and stall wherever the gradient eases or a joint interrupts them, building a blockage. Codes cap branch slopes at about 15%, beyond which you use a backdrop or a larger pipe. It is the opposite of supply pipe logic, which catches people out.
What matters with floor drains and traps?
Use a trapped gully with a seal at least 50 mm deep, or sewer gas comes back — the commonest cause of bathroom smells. Traps need the same 50 mm seal, and rarely used drains must be topped up. Branch runs beyond about 4-6 m need a rodding eye, or a blockage cannot be cleared.
Is rainwater pipe sloped like drainage?
No. Rainwater carries high flow and grit but little organic matter, so slopes can be gentler — 1% at DN100 — while the upper velocity limit is stricter, 5 m/s, to prevent erosion. The base of a roof downpipe needs an energy dissipator, since water falling ten metres or more hits hard. Storm and foul must be kept separate; cross-connection fails environmental inspection.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Drainage Pipe Slope Calculator. 2026-10-25. https://jianzhujisuan.com/en/drain-slope

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.