算BuildCalc Get a quote

Ringlock Scaffold Calculator (by component)

Ringlock take-off by component: standards, ledgers, braces and bases, in pieces and tonnes.

Also known as ringlock scaffold · cuplock scaffold · modular scaffold

Quick answer

With the default inputs: Building length 30 m · Building width 14 m · Height 24 m etc.Total ringlock weight 27.86 t

Use your own dimensions ↓

Inputs

Long side of the building; the scaffold on all four sides is worked out automatically from length and width
Short side of the building; together with the length it sets the scaffold quantity, with extra continuous braces at corners
At 24 m and above braces tighten from 4 bays to 3; 50 m and above needs expert review
Stock sizes 0.6-2.4; 2.4 is the longest ledger made
Usually 0.9 or 1.2; 2.4 maximum
1.5 or 2.0 only, since braces are only made in those two rises
Standard lengths in stock (tick each one your depot actually has)
Unticked lengths are never used in the make-up; keep at least one. A 3.0 m standard is listed in Table A.0.1, but many depots do not stock it.
Normal facade work is two rows. Three or four rows widen the platform; frame width = (rows - 1) x transom spacing
levels
Fully decked working levels, usually 2

Result

Total ringlock weight
27.86t
Building length30.0m
Building width14.0m
Total height24.0m
Facade area2112m²
Bays59bays
Rows of standards2rows
Frame width0.9m
Standards (2 rows)120bars
Standard make-up per leg3000×8
Lengths per leg8
Splices per leg7
Total standard splices840pcs
Standards excl. bases14064kg
Ledger levels17levels
Longitudinal ledgers B-SG-15002006bars
Transoms B-SG-9001020bars
Ledger weight11482kg
Brace interval3bays
Brace columns (outer face)20columns
Braces B-XG-1500x1500320bars
Brace weight1843kg
Adjustable bases B-XT-600120pcs
Adjustable base weight467kg
Ties (<=3 bays, <=2 lifts)180pcs
Total component weight27856kg
In tonnes27.86t
Steel per m² of facade13.19kg/m²
Decking area158m²
How this is worked out

Weight is the sum of the tabulated unit mass of each component in DB11/T 2100-2023 Table A.0.1, not run-length times mass per metre. The difference is real: Φ48.3x2.5 tube alone is 2.82 kg/m, yet ledger B-SG-1200 is nominally 1200 mm, actually 1152 mm, and weighs 3.60 kg — a per-metre estimate gives 3.38 kg and understates by 6%, the gap being the two end connectors. Procure by type, so weigh by type. Vertical braces are counted on the outer face only, per JGJ/T 231-2021 clause 6.3.5 item 3 (continuous from base to top between adjacent standards on the outer face); if a project braces both faces, double the brace count and weight. The same holds for three- and four-row frames: braces are still counted on the outer face only, because every construction clause in section 6.3 (lift, staggered first lift, access openings, vertical braces) is written for a two-row working scaffold, and nothing in the standard says how to brace the inner face or the middle rows of a three- or four-row frame — that is for the method statement to fix and must be added by hand. Ties are laid out by bay and lift count and likewise do not change with the number of rows. The brace interval follows item 2 of the same clause: not more than four bays apart, tightened to not more than three bays where the scaffold is 24 m or higher. 24 m is included — read it as "above 24 m" and a 24.0 m run keeps the four-bay spacing, giving 15 brace columns and 240 braces where three-bay spacing gives 20 columns and 320 braces, 80 braces short. Columns are counted from the first brace at the start of the run, one every interval (floor + 1, not ceil) — 30 bays at three-bay spacing gives 11 columns, not 10. The model is a single straight run: the length and width you enter are developed as (length + width) x 2 around all four sides; a short final bay is not closed off, but clause 6.3.5 item 1 requires continuous braces at corners and at the ends of an open-ended scaffold, so those have to be added by hand either side of a corner or a free end. Levels and brace lifts are derived from the height you enter (floor + 1); where the height is not a multiple of the lift, site practice is to add one more lift to reach a whole number, so an entered 23.9 m is built to 24.0 m and needs one extra level of ledgers and one extra brace lift — check against the height actually built. Standards are made up from only the lengths you tick as in stock (six stock sizes 3000/2500/2000/1500/1000/500, each with its own switch) with the remainder taken by the adjustable base, normally within 300 mm. A 3.0 m standard is a standard component — Table A.0.1 lists B-LG-3000 at 14.65 kg, it is not invented; but depots stock different ranges and many stop at 2.5 m, hence six independent switches, one per length, so any mix of stock can be matched. The count of splices follows the set: at 24 m the full set gives eight lengths and seven splices per leg, whereas with nothing longer than 2.5 m the make-up is 2.5x8 + 2.0x2, ten lengths and nine splices — two extra splice sections per leg that must be staggered by at least 500 mm (clause 6.3.2 requires splices staggered level by level), which over 120 standards is 240 extra splices. The connecting collar is welded to one end of the standard and is part of it (clause 2.1.11), so nothing extra has to be stocked for it; what does have to be stocked is the standard connecting pin, one per splice. Staggering is the part that matters: the commentary to clause 5.2.1 of DB11/T 2100-2023 is blunt about it — the splice is the weak section of a standard, and when splices all land on one level the horizontal force puts some standards into tension and makes them buckle. So what this tool gives is how many lengths one standard is made of; on site adjacent standards must start with different lengths so that the splices sit at different levels, rather than all 120 being built the same way. Excluded: decking and fine-mesh net self-weight (use the product declared mass), toe boards, the extra continuous bracing required at corners and open ends, and the tie members themselves. This is a material take-off, not a design or a method statement. A ground-bearing tube scaffold 24 m or higher is classed as high-risk temporary works, and 50 m or more requires expert review.

Next up: Ringlock Shoring Calculator (Slab Soffit) · Ringlock Beam Shoring Calculator (Under-Beam Densification)

Formula

Facade areaS = (length + width) x 2 x height (m x m = m²); the scaffold wraps all four sides and is taken off as one straight run; the frame's own width (transom spacing) is not part of the facade area
Baysn = ceil[(length + width) x 2 ÷ bay length]
Rows of standardsUse 2 rows for ordinary facade work. Three or four rows widen the platform and change only four quantities: standards, longitudinal ledgers, transoms and adjustable bases
Frame widthB = (rows - 1) x transom spacing (m); the transom spacing is the gap between adjacent rows, not the width of the frame
StandardsN = (bays + 1) x rows of standards (2 by default)
Standard make-upComplete-knapsack over the ticked lengths only (six stock sizes 3000/2500/2000/1500/1000/500, each can be marked out of stock), lightest make-up with total length within [height-0.3, height+0.5]; remainder taken by the base jack
Standard splicesSplices per leg = lengths - 1; total = standards x (lengths - 1), staggered by at least 500 mm
Ledger levelsn = floor(height ÷ lift) + 1, including the bottom sweep and the top level
Longitudinal ledgersN = levels x bays x rows, one per row
TransomsN = levels x (bays + 1) x (rows - 1); one links each pair of adjacent rows, so two rows take one, three take two, four take three
Brace interval3 bays where height is 24 m or more, otherwise 4 bays (clause 6.3.5 item 2)
Brace columnsN = floor(bays / interval) + 1; the run must start with a brace, so ceil is wrong
Vertical bracesN = columns x floor(height / lift). This does not rise with the number of rows: clause 6.3.5 covers the outer face of a two-row scaffold only, so bracing the inner face or the middle rows of a three- or four-row frame is a method-statement decision
Adjustable basesN = number of standards; a facade scaffold uses bases, not head jacks
TiesN = [floor(bays / 3) + 1] x [floor(lifts / 2) + 1]
WeightW = sum of quantity × unit mass from Table A.0.1
A 30 m by 14 m building wrapped on all four sides, 24 m high, 1.5 m bays, 0.9 m transoms, 1.5 m lifts: 59 bays, 120 standards (each eight 3000 mm lengths), 17 ledger levels, 2,006 longitudinal ledgers and 1,020 transoms, and because 24 m trips the three-bay rule, 20 brace columns x 16 lifts = 320 braces plus 120 adjustable bases — about 27.9 t, or 13.2 kg per m² of facade. With three rows: 180 standards, 2,040 transoms, about 42.3 t; with four rows: 240 standards, 3,060 transoms, about 56.7 t — three rows is not 1.5 times and four is not 2 times, because the transoms double and treble.

How to work it out

  1. Bays = (length + width) x 2 divided by bay length, rounded up; the four sides are taken off as one straight run, so you do not have to work it out yourself. Standards = (bays + 1) x rows of standards, two rows for ordinary facade work. The plus one is because each end of the run needs a standard; it is not the number of rows.
  2. The number of rows only changes when the platform has to be widened; ordinary facade scaffolding is two rows. Rows change exactly four quantities: standards x rows, longitudinal ledgers x rows, transoms x (rows - 1), and adjustable bases equal to the number of standards. Vertical braces and ties do not follow the row count. That is why three rows is 1.52 times two rows rather than 1.5, and four rows is 2.04 times rather than 2.0: the same 30 m by 14 m building at 24 m gives 27.86 t on two rows, 42.29 t on three and 56.72 t on four. Frame width = (rows - 1) x transom spacing, so three rows at 0.9 m transoms is a 1.8 m wide platform, not 0.9 m.
  3. Make up each standard from stock lengths 3000/2500/2000/1500/1000/500 and leave no more than 300 mm to the adjustable base. Ringlock standards are fixed-length components: a 5 m leg is a 3000 plus a 2000, not one 5 m piece. A 3.0 m standard is a standard component listed in Table A.0.1, but depots stock different ranges, so tick only the lengths your depot actually holds — each of the six has its own switch; switching one off adds splices, taking a 24 m leg from seven to nine, and those splices must be staggered by 500 mm level by level.
  4. Ledger levels = floor(height / lift) + 1. The plus one covers the bottom sweep and the top level; using ceil instead adds a whole level at non-integer lift counts, which on a 24 m scaffold at 1.5 m lifts is roughly 600 kg of extra steel.
  5. Vertical braces turn on the 24 m line: at 24 m and above, one brace every three bays; below 24 m, every four bays. Columns = floor(bays / interval) + 1, minimum two, because the run has to start with a brace; braces = columns x lifts, each column continuous from base to top. Thirty bays at three-bay spacing is 11 columns, not 10, and that is the easiest line to undercount.
  6. Total weight is the sum of quantity times the tabulated unit mass of each component type, then divided by the facade area to give steel per square metre for comparison against similar scaffolds.

Where it goes wrong

Material and cost

Ringlock is rented by the tonne-day or the square-metre-day, and rates vary widely between depots and with hire duration and whether erection labour is included, so no single rate is quoted here. When comparing quotes, pin down three things: charged by tonne or by area, whether delivery and collection are included, and the loss-and-damage rate per missing piece. Erection and dismantling labour is normally priced separately, by facade area or by tonne.

On site

Basis

FAQ

How do I work out a three- or four-row scaffold, and how far off is it from two rows?
The number of rows changes only four quantities: standards = (bays + 1) x rows; longitudinal ledgers = levels x bays x rows, one per row; transoms = levels x (bays + 1) x (rows - 1), one linking each pair of adjacent rows, so two rows take one, three take two and four take three; adjustable bases = number of standards. Vertical braces and ties do not change with the number of rows. So three rows is not 1.5 times and four rows is not 2 times: at 88 m long, 24 m high, 1.5 m bays, 0.9 m transoms and 1.5 m lifts, two rows give 120 standards and 27.86 t, three rows give 180 standards and 42.29 t (1.52 times), and four rows give 240 standards and 56.72 t (2.04 times) — the difference comes from the transoms doubling and trebling. One more thing that catches people out: the transom spacing is not the frame width. Frame width = (rows - 1) x transom spacing, so three rows at 0.9 m transoms give a 1.8 m wide platform. A final caution: every construction clause for working scaffolds in section 6.3 of JGJ/T 231-2021 is written for two rows (lift, staggered first lift, access openings and vertical braces all say two-row), so three and four rows go beyond the standard construction rules and need a specific method statement; whether the inner face or the middle rows need braces is not addressed, so that has to be added by hand on top of what this tool gives.
At 24 m exactly, is it four bays or three?
At 24 m exactly, use three. Clause 6.3.5 item 2 of JGJ/T 231-2021 reads that where the scaffold height is 24 m or above, a vertical brace shall be provided at intervals of not more than three bays. The Chinese wording includes the boundary value, so 24.0 m itself takes three-bay spacing rather than waiting for 24.1 m. Four independent sources agree word for word, including two municipal housing-authority hazard catalogues and the standard text itself. The cost of getting it wrong is concrete: a 30 m by 14 m building at 24 m gives 15 brace columns (240 braces) at four bays against 20 columns (320 braces) at three, a shortfall of 80 braces and roughly 460 kg. The same 24 m is also the trigger for high-risk temporary works under MOHURD circular No. 31 of 2018, so one height trips two separate rules and both include the boundary.
Why can't I just multiply tube length by mass per metre?
Because ringlock members carry a connector at each end, so the weight is not the tube weight. Φ48.3x2.5 tube alone is indeed 2.82 kg/m, but ledger B-SG-1200 is nominally 1200 mm, actually 1152 mm, and tabulated at 3.60 kg — a per-metre estimate gives 3.38 kg and understates by 6%. Braces diverge further: B-XG-1500x1500 has an actual length of 2004 mm and weighs 5.76 kg, while 2.82 kg/m gives 5.65 kg, and its horizontal projection bears no simple relation to its diagonal length anyway. Procurement is by piece and by type, quotations and site acceptance are by type, so the take-off must be by type too. This is the essential difference from coupler scaffolding: coupler tube is plain tube and can be estimated per metre, whereas ringlock members are finished components that can only be looked up.
What counts as high-risk, and when is expert review needed?
A ground-bearing tube scaffold 24 m or higher is high-risk temporary works and needs a specific method statement that has been reviewed and approved; 50 m or higher is above-scale high-risk and requires expert review. The basis is the two annexes to MOHURD circular No. 31 of 2018, annex 1 for the high-risk scope and annex 2 for the above-scale scope. Two things to note: both thresholds are inclusive, and a ringlock system does not escape the method statement on the grounds of higher capacity — the classification turns on height and form, not member strength. Building without the required review carries, under Order 37 article 34, a correction notice, a fine of CNY 10,000 to 30,000, a 30-day suspension of the safety production licence, and a further CNY 1,000 to 5,000 on the responsible person.
What is the difference between an adjustable base and a head jack?
A facade scaffold needs adjustable bases only, not head jacks. A base jack sits under the standard, transfers load to the ground and adjusts height; a head jack sits on top of the standard and is used on shoring scaffolds to carry primary beams and beam soffit formwork. They are not interchangeable and their masses differ: standard B-XT-600 base is 3.89 kg and B-XT-500 is 3.53 kg, while B-ST-600 head jack is 4.74 kg and B-ST-500 is 4.38 kg. Heavy-duty Z types are heavier again, Z-XT-600 at 6.15 kg and Z-ST-600 at 7.60 kg. Including head jacks in a facade take-off overstates the order; omitting them from a shoring take-off leaves the top level with nothing to adjust when the beam soffit goes on.
Our depot has no 3 m standards. Can I still use this?
Yes — set the 3.0 m standard switch to 'Not stocked' and leave the other five ticked. Each of the six lengths has its own switch, so switch off exactly what your depot lacks rather than fitting a preset set. First, the facts: a 3.0 m standard is a standardised component. Table A.0.1 of DB11/T 2100-2023 lists B-LG-3000 at 14.65 kg, and depots in Tianjin and Langfang publish 0.5 to 3.0 m as their normal range. So the length does exist; what varies is what each depot stocks, and plenty stop at 2.5 m, which is entirely normal on site. The cost of losing the 3.0 m length is more splices. At 24 m the full set gives eight lengths and seven splices per leg; with 2.5 m as the maximum the make-up is 2.5x8 + 2.0x2, ten lengths and nine splices, so 120 standards carry 240 extra splices. One thing worth getting right before ordering: the connecting collar is not a separate fitting — it is welded to one end of the standard and is part of the component (clause 2.1.11), so extra splices do not mean renting extra collars; what you do need is the standard connecting pin, one per splice. The real difficulty is staggering. Clause 6.3.2 requires splices to be staggered level by level with at least 500 mm between adjacent ones, and the commentary to clause 5.2.1 of DB11/T 2100-2023 spells out why: with every splice on one level, a horizontal force puts some standards into tension and makes them buckle. Going from seven splices to nine leaves less room to stagger, so the bottom lift has to alternate standard lengths rather than splicing every standard at the same height. If the depot cannot even supply 2.5 m, change depot rather than building up from 1.5 m lengths — splices that dense compromise the integrity of the frame.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Ringlock Scaffold Calculator (by component). 2026-10-25. https://jianzhujisuan.com/en/ringlock-scaffold

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.