Ringlock Shoring Calculator (Slab Soffit)
Slab soffit shoring: standards, ledgers both ways, vertical braces and head jacks, in pieces and tonnes.
Also known as shoring calculation · falsework design · slab shoring
With the default inputs: Shoring footprint, length 24 m · Shoring footprint, width 18 m · Shoring height 6 m etc.Total ringlock weight 27.11 t
Use your own dimensions ↓Inputs
Result
| Total length | 24.0m |
| Total width | 18.0m |
| Total height | 6.0m |
| Footprint area | 432m² |
| Frame volume | 2592m³ |
| Bays, length way | 20bays |
| Bays, width way | 15bays |
| Total standards | 336bars |
| Actual standard length | 5.50m |
| Standard make-up per leg | 3000×1 + 2500×1 |
| Lengths per leg | 2 |
| Total standard splices | 336pcs |
| Standard weight | 9055kg |
| Ledger levels | 5levels |
| Longitudinal ledgers B-SG-1200 | 1600bars |
| Transverse ledgers B-SG-1200 | 1575bars |
| Ledger weight | 11430kg |
| Brace class, Table 6.2.2-1 | Every 3 bays |
| Braces B-XG-1200x1500 (length way) | 336bars |
| Braces B-XG-1200x1500 (width way) | 378bars |
| Vertical braces, both directions added | 714bars |
| Brace weight | 3727kg |
| Head jacks B-ST-600 | 336pcs |
| Base jacks B-XT-600 | 336pcs |
| Head jack projection (limit 400) | 350mm |
| Base jack projection (limit 300) | 0mm |
| Jack weight | 2900kg |
| Total component weight | 27112kg |
| In tonnes | 27.11t |
| Steel per m² of footprint | 62.8kg/m² |
| Steel per m³ of frame | 10.5kg/m³ |
| Horizontal brace courses, every 6 lifts | 1courses |
| Tie courses (H above 8 m) | 0courses |
| Height-to-width ratio | 0.33 |
| Total design load, back-calculated | 11.7kN/m² |
| High-risk classification | High-risk: method statement required |
How this is worked out
Vertical braces run both ways, and that is the biggest difference between shoring and a facade scaffold. A facade scaffold braces the outer face only, per clause 6.3.5 item 3; shoring follows Table 6.2.2-1 under clause 6.2.2 and is braced in both plan directions at once. On the same 24 x 18 m frame the facade rule gives 20 brace columns while the shoring rule gives two sets of 16 x 7 and 21 x 6 — close to five times the quantity. Apply the facade method to shoring and the braces will arrive at less than half of what the site needs. Reading the class: Table 6.2.2-1 (standard type B, standard 1.5 m lift) is entered with the design axial force N and the height H. For N up to 25 kN use three-bay spacing up to 16 m, two-bay from 16 to 24 m and single-bay above 24 m; for 25 to 40 kN use two-bay up to 8 m and single-bay above; for N above 40 kN at a height above 24 m every bay must be braced. N is the maximum within one independent frame, not the average — one overloaded corner sets the class for the whole frame. Where the height exceeds 16 m the top lift is braced in every bay as well (clause 6.2.3); that lift is counted separately and must not be added on top of the normal arrangement twice. The top carries head jacks, not bases: every standard of a shoring frame takes an adjustable head jack (clause 6.2.2), with the projection above the top ledger not exceeding 650 mm, the screw exposed not more than 400 mm and at least 150 mm inserted (clause 6.2.4); the base jack screw needs at least 150 mm inserted and should not project more than 300 mm, and the bottom ledger centreline must sit within 550 mm of the base plate (clause 6.2.5). Head jack B-ST-600 weighs 4.74 kg and base jack B-XT-600 3.89 kg; they are not interchangeable. The standard length is not free to choose, and this is the easiest place to get the take-off wrong. Ledgers sit on the rosettes, so the distance from the top of the standard to the soffit can only be absorbed by the head jack and the base jack — up to 400 mm of head jack projection and 300 mm of base jack projection, 700 mm together, less roughly 150 mm for bearers, joists and sheeting. The standards must therefore total between height minus 0.85 m and height minus 0.15 m; outside that window the site cannot adjust it back. On a 6.0 m clear height the standards can only be 5.15 to 5.85 m, so they make up 5.50 m (3000 plus 2500) and the remaining 0.50 m is taken by 350 mm of head jack and no base projection. Pick the length set before you trust the make-up. On the full set that is a 3000 and a 2500, two lengths and one splice; a depot that stops at 2.5 m needs 2000 plus 2000 plus 1500, three lengths and two splices, which on the same 24 x 18 m frame adds about 170 kg and doubles the splice count. Splices must also be staggered lift by lift under clause 6.3.2, at least 500 mm apart, never gathered at one level. Count ledger levels with ceil plus one, not floor plus one. A 5.50 m standard at 1.5 m lifts carries ledgers at 0, 1.5, 3.0, 4.5 and 5.5 — five levels. Floor plus one gives four, leaving the top ledger at 4.5 m and asking the head jack to reach 1.5 m, where clause 6.2.4 allows 650 mm. That is exactly why head jacks on site bottom out with a gap still showing. Vertical braces are counted over whole lifts only, since the closing length at the top has no brace made to suit it. Three structural limits: keep the height-to-width ratio within 3, otherwise tie rigidly to an existing structure or add anti-overturning measures (clause 6.2.1); above 8 m with an existing structure adjacent, tie back every four to six lifts (clause 6.2.6); and provide a horizontal brace course every four to six standard lifts (clause 6.2.7). This tool reports horizontal brace courses and tie courses as counts only, because both are built from coupler tube rather than ringlock components — weigh them separately against the full-scaffold page. Weight basis: every figure is the sum of tabulated unit masses from Table A.0.1, never run-length times mass per metre. Keep the two intensities apart: `kg/m²` is per square metre of footprint and `kg/m³` is per cubic metre of frame; on a 5 m high frame they differ five-fold, so say which one you mean when you quote a depot or a client. Not included: bearers, joists, formwork sheeting, sole boards, coupler-tube bracing, safety netting, and the strengthening beams around access openings. High-risk classification follows MOHURD circular No. 31 of 2018: formwork support at 5 m or above, span 10 m or above, total design load 10 kN/m² or above, or line load 15 kN/m or above is high-risk and needs a specific method statement; 8 m, 18 m, 15 kN/m² or 20 kN/m or above is above-scale and requires expert review. The four conditions are alternatives, so any one escalates the job. The tool tests only two of them: height comes straight from your input, and total load is back-calculated as standards times axial force over footprint. Span and concentrated line load depend on the structural grid and the beam section, which this tool does not ask for and will not guess — so the verdict can only err on the lenient side. When it says the work is below the threshold, check the column grid and the beam line load yourself, and do not skip that check on long-span beams, transfer levels or beside pour strips. This is a material take-off, not a substitute for the shoring design or the method statement.
Next up: Ringlock Scaffold Calculator (by component) · Ringlock Beam Shoring Calculator (Under-Beam Densification)
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Bays, length way | nx = ceil(footprint length ÷ standard spacing) |
| Bays, width way | ny = ceil(footprint width ÷ transom spacing) |
| Standards | N = (nx + 1) x (ny + 1) |
| Standard make-up | Complete knapsack over the ticked lengths only (six stock sizes, each switchable), with total standard length constrained to [height - 0.85, height - 0.15]; the remainder is taken by head and base jacks |
| Ledger levels | n = ceil(actual standard length ÷ lift) + 1; the closing length needs a ledger, otherwise the head jack projection exceeds 650 mm |
| Longitudinal ledgers | N = levels x (ny + 1) x nx, each of bay length |
| Transverse ledgers | N = levels x (nx + 1) x ny, each of transom spacing |
| Brace class k | From Table 6.2.2-1 by axial force N and height H: N up to 25 gives 3 bays up to 16 m, 2 to 24 m, 1 above; 25 to 40 kN gives 2 up to 8 m, 1 above; above 40 kN gives every bay above 24 m, 1 otherwise |
| Braces per lift, length way | (ny + 1) x [floor(nx ÷ k) + 1]; for every bay (k=0) use (ny + 1) x nx |
| Braces per lift, width way | (nx + 1) x [floor(ny ÷ k) + 1]; for every bay (k=0) use (nx + 1) x ny |
| Top lift above 16 m | Above 16 m the top lift is braced in every bay, and the normal arrangement counts only (lifts - 1) |
| Head jacks | N = number of standards; every standard takes one |
| Base jacks | N = number of standards |
| Horizontal bracing | Courses = floor(lifts ÷ 6) + 1; coupler tube, excluded from ringlock weight |
| Structural ties | Above 8 m, courses = floor(lifts ÷ 6) + 1 |
| Footprint area | S = total length x total width (m x m = m²) |
| Frame volume | V = total length x total width x total height = footprint area x total height (m x m x m = m³) |
| Weight | W = sum of quantity x unit mass from Table A.0.1 |
| High-risk test | High-risk if height >= 5 m or total load >= 10 kN/m²; expert review if height >= 8 m or load >= 15 kN/m². Span and concentrated line load are not tested here and must be checked separately |
How to work it out
- Count the grid first: bays along the length are the footprint length divided by the standard spacing, rounded up, and bays across likewise; standards are (bays along + 1) x (bays across + 1). The plus one at each edge is because a full shoring frame has a row of standards on all four sides, not one fewer at the boundary.
- Set the standard length. This is where most take-offs go wrong. The distance from the top of the standard to the soffit can only be absorbed by the head jack and the base jack, at up to 400 mm and 300 mm respectively, less about 150 mm for bearers, joists and sheeting. The standards must therefore total between height minus 0.85 m and height minus 0.15 m. At a 6 m clear height the standards can only be 5.15 to 5.85 m, so they make up 5.50 m from a 3000 and a 2500, with 350 mm of head jack taking the rest.
- Ledger levels are the actual standard length divided by the lift, rounded up, plus one. A 5.50 m standard at 1.5 m lifts carries ledgers at 0, 1.5, 3.0, 4.5 and 5.5, five levels. Floor plus one gives four and leaves the top ledger at 4.5 m, asking the head jack to reach 1.5 m where the code allows 650 mm — the frame simply cannot be built that way. The closing length at the top needs a ledger to lock the standard head.
- Look the vertical braces up rather than guessing. Table 6.2.2-1 of JGJ/T 231-2021 (standard type B, 1.5 m standard lift) is entered with the design axial force N and the height H. For N up to 25 kN use three-bay spacing up to 16 m, two-bay from 16 to 24 m and single-bay above 24 m. For 25 to 40 kN use two-bay up to 8 m and single-bay above. Above 40 kN at a height above 24 m every bay is braced. N is the maximum within one independent frame.
- Braces run both ways: one plane in every row of standards along the length, one plane in every column across the width, each at the interval from the previous step. Every plane runs continuously from base to top, so the count is planes times whole lifts, with the closing length left unbraced because no brace is made for it. Above 16 m the top lift is braced in every bay, counted separately and never added on top of the normal arrangement twice.
- Fit one head jack and one base jack per standard and check both projections. What remains is coupler tube work: a horizontal brace course every four to six standard lifts, and a tie to the existing structure every four to six lifts above 8 m. Neither is a ringlock component, so weigh them separately.
Where it goes wrong
- Applying the facade scaffold method to shoring — a facade scaffold braces the outer face only, whereas shoring is braced in both plan directions. On the same 24 x 18 m frame that is 320 braces against 714, a factor of 2.2; order on the facade figure and the site ends up without enough braces to make the frame geometrically stable.
- Counting ledger levels with floor plus one — that is the facade rule, and on shoring it drops the closing level at the top. At 6 m clear height and 1.5 m lifts one level is missed, which on 336 standards is 3,360 ledgers, about 12 tonnes.
- Treating the shoring height as the standard length — standards, head jacks and base jacks add up. Order 6 m standards for a 6 m clear height and the frame finishes half a metre above the soffit, leaving the site to cut standards down or force them in.
- Leaving out the head jacks — every standard of a shoring frame takes one, where a facade scaffold has bases only. On 336 standards that is 1,593 kg missing, and worse, nothing to adjust when the bearers go on.
- Inventing the brace class — the usual shortcut is four-bay spacing because that is the facade rule. Table 6.2.2-1 depends on N and H, and above 40 kN at over 24 m every bay is braced, which changes the whole brace order.
- Comparing kg/m² directly with the rule of thumb of 30 kg per square metre — that figure is usually per square metre of floor area at around 3 m storey height, while shoring quantity scales with height. A 6 m frame at 60 kg/m² is normal; measured against 30 it looks over-designed and the cutting starts. Compare kg/m³ instead, where shoring sits at 8 to 15.
Material and cost
Ringlock shoring is rented by the tonne-day or square-metre-day with wide regional variation and strong dependence on hire period and whether erection is included, so no unit rate is quoted. Pin down four things when comparing quotes: charged by tonne or by area, and if by area whether it is floor area or shoring footprint; whether delivery and collection are included; the loss-and-damage rate; and whether head and base jacks are priced separately. Labour is separate, and high formwork adds the cost of the method statement and expert review.
On site
- Height 5 m or above, span 10 m or above, total design load 10 kN/m² or above, or line load 15 kN/m or above makes it high-risk and requires a method statement; 8 m, 18 m, 15 kN/m² or 20 kN/m or above is above-scale and requires expert review. The conditions are alternatives. This tool tests height and total load only, so check span and line load yourself.
- Keep the height-to-width ratio within 3 (clause 6.2.1). Beyond that, tie rigidly to an existing structure or add anti-overturning measures, or the horizontal force at the pour will push the whole frame over — in these failures the members are usually strong enough and the frame loses on overall stability.
- Above 8 m with an existing structure adjacent, tie back every four to six lifts (clause 6.2.6). Ties are not optional: they are how horizontal force reaches the structure, and no amount of bracing substitutes for them.
- A horizontal brace course every four to six standard lifts (clause 6.2.7), built from coupler tube and never from ringlock ledgers. Ringlock quotations do not include this, and the shortfall appears on site when the frame is already up — list it separately at the take-off stage.
- Sole boards under every standard, at least 50 mm thick and spanning two bays, on compacted ground with drainage. Uneven settlement is the most common cause of shoring collapse, more common than a shortage of members and far easier to overlook.
- Inspect before the pour: spacing, lift, brace count, jack projection and whether the wedges are driven home. Ringlock wedge seating should be within 3 mm, and wedges set in place but not hammered are a routine failure — check them one by one.
Basis
- EN 12812:2008 Falsework — Performance requirements and general design
- EN 12813:2004 Temporary works equipment — Load bearing towers of prefabricated components: particular methods of structural design
- BS 5975:2019 Code of practice for temporary works procedures and the permissible stress design of falsework
- ACI 347R-14 Guide to Formwork for Concrete
- OSHA 29 CFR 1926.703 (requirements for cast-in-place concrete)
FAQ
Why does shoring need so many more braces than a facade scaffold?
Where does the design axial force N in Table 6.2.2 come from if I have no calculation?
Is the horizontal bracing in clause 6.2.7 a ringlock component? Should it be in the tonnage?
Is it 5 m or 8 m that triggers expert review?
Why can the lift only be 1.5 or 2.0 m when our method statement says 1.8 m?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Ringlock Shoring Calculator (Slab Soffit). 2026-10-25. https://jianzhujisuan.com/en/ringlock-shoring