算BuildCalc

Voltage Drop Calculator

Percentage voltage drop with a 5% compliance check.

Quick answer

With the default inputs: Load 5 kW · Nominal voltage 380 V · Phase Three phase 380 V etc.Voltage drop 0.76%

Edit the inputs below to recalculate.

Inputs

kW
V
mm²
One-way length

Result

Voltage drop
0.76%
Design current8.94A
Loop resistance0.2188Ω
Voltage drop2.88V
Voltage at load377.1V
Limit5%
VerdictPass
Max length at this size330.1m
Min size for 5%0.61mm²
Drop per 100 m1.51%

The simplified forms ΔU = √3·I·R·cosφ for three phase and 2·I·R·cosφ for single ignore reactance, which is fine below 120 mm². Guidance limits: 5% for lighting and power, relaxed to 8% for temporary site supplies. Excessive drop makes motors hard to start, overheats them and shortens life.

Formula

Three-phase currentP ÷ (√3 × U × cosφ)
Resistanceρ × L ÷ S
Three-phase drop√3 × I × R × cosφ
Single-phase drop2 × I × R × cosφ
PercentageΔU ÷ U × 100
Max lengthL × 5 ÷ percentage
5 kW at 380 V on 50 m of 4 mm² copper at 0.85 power factor: 8.94 A, 0.2188 Ω, a 2.88 V drop and 0.76% — a pass. The same cable at 30 kW drops 4.55%, close to the limit.

How to work it out

  1. Compute the current first: three-phase I = P ÷ (√3 × U × cosφ), single-phase I = P ÷ (U × cosφ). Rated current is not operating current — full load and light load differ widely.
  2. Work out conductor resistance R = ρ × L ÷ S, with ρ = 0.0175 Ω·mm²/m for copper and 0.0283 for aluminium. L is the one-way length.
  3. Three-phase drop is ΔU = √3 × I × R × cosφ. A single-phase circuit carries current out and back through two conductors, so ΔU = 2 × I × R × cosφ. Dropping that factor of 2 is the classic error.
  4. Divide by nominal voltage for the percentage. Limits: ±5% at motor terminals, ±5% for other utilisation equipment, -10% to +5% for lighting in general workplaces, and up to 10% momentarily during motor or fire-pump starting.
  5. If it fails there are three remedies: larger cross-section, shorter run, or a substation moved closer. Copper cost rises with the square of the size while rerouting is nearly free, so check the route first.
  6. Run it backwards: with a 5% allowance, the maximum feed length is Lmax = L × 5 ÷ drop%, which sets the service radius of a distribution board.

Where it goes wrong

Material and cost

One size up costs roughly 50% more at 4→6 mm², 60% at 6→10 mm² and 55% at 10→16 mm². On runs beyond 100 m, adding an intermediate distribution board is usually cheaper than upsizing: 800-2000 CNY per board including enclosure, breakers and mounting, at the price of an extra level of discrimination to design.

On site

Basis

FAQ

Why 2 for single phase and √3 for three?
Because a single-phase circuit has an out and a return leg, so there are two lengths of resistance and the drop doubles. In three phase the currents are 120° apart and vector summation gives √3 ≈ 1.732, not 2 or 3. Swapping these factors is the commonest calculation error and shifts the answer by over 15%.
Why not just use a bigger cable on long runs?
Because cost turns sharply once the size grows: capital rises linearly with area while losses fall with the square of the inverse, so there is an economic size. Beyond it the saved energy no longer pays for the copper. The usual answer for loads over 200 m is a local distribution board, or distributing at higher voltage and transforming on site.
What does low voltage actually do?
Motors suffer most: a 10% drop cuts torque by about 19% since torque goes with the square of voltage, while starting current rises, starts take longer, windings run hotter and life halves. Lighting shows it as dimmed incandescent lamps, reluctant fluorescents and unstable LED drivers. The code limit protects equipment, not just brightness.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Voltage Drop Calculator. 2026-10-25. https://jianzhujisuan.com/en/voltage-drop

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.