算BuildCalc Get a quote

Scaffolding Calculator

Enter the scaffolded length and height (plus the second side for four sides) to get the area, tube, coupler and board quantities.

Also known as scaffold tube and fitting · scaffold material takeoff · tube and coupler

Quick answer

With the default inputs: Length scaffolded 80 m · Second side 0 m · Scaffold height 20 m etc.Scaffold area 1600.0 m²It is 4.0 metres per m² or 5.9 — both are right. Counting standards and mid-rails only gives 4.01 m, the familiar "4 metres per square"; add base ledgers, bracing, ties and guard rails with toe boards and a member take-off gives 5.90 m. Counting standards, ledgers and transoms alone gives 2.91 m — the "3 metres per square" seen online simply omits base ledgers and bracing. The per-m² figure tracks layout, hardly height: from 12 m to 48 m it only falls from 3.9 to 3.5. Couplers follow the layout: 2.6 per m² at 1.5x1.8 with one mid-rail, 4.3 at 1.5x1.5 with two; the 3.0 in the result rows is a rounded allowance, so order 4.3 on a double mid-rail. For four sides (atrium, shaft) enter length and width and the perimeter becomes 2 x (length + width).

Use your own dimensions ↓
Length LWidth W
Measured on the vertical elevation of the facade; openings are usually not deducted.

Inputs

One wall: that wall's length. Four sides (atrium, shaft, lift well): one side, with the other in the next field
For four sides, the adjacent side; perimeter becomes 2 x (length + width). Enter 0 for a single wall
Ground to eaves or parapet top
kg/m²
15.5-17.5 kg/m² for double-row (about 4.1-4.5 m of tube per m²); single row about 11-12
Distance between inner and outer standards; 1.05 m is typical (0.9-1.3)
levels
Levels boarded at the same time; 2 for finishing, 1 plus a protective level every 10 m for structure; enter 0 for a bare frame (tube and couplers only)

Result

Scaffold area
1600.0m²
Lifts @1.8 m12lifts
Scaffold area1600.0m²
Perimeter80.0m
Steel tube (bare)26.40t
6 m tubes1146bars
Couplers per 6 m tube4.19pcs
Couplers (about 3.0 per m²)4,800pcs
Coupler weight (1.34 kg each)6.43t
Board area (2 levels × 1.05 m)168.0m²
Board weight (25 kg/m²)4.20t
Safety netting1680.0m²
Netting weight (about 0.21 kg/m² actual)0.35t
Total self-weight (for procurement)37.38t
Self-weight per m² (procurement)23.4kg/m²
Self-weight at code values (for checking)39.69t
Self-weight per m² (design values)24.8kg/m²
Wall ties (3 lifts × 3 bays)72pcs
Take-off tube per m² (1.5 bays, 1.8 lifts, one mid-rail)3.85m/m²
Take-off tube total (with bracing and rails)23.62t
Take-off couplers per m²2.58pcs/m²
Take-off couplers total (incl. 3% wastage)4,124pcs
How this is worked out

The 16.5 kg/m² figure is bare tube only — standards, ledgers and bracing. Add about 4.0 for couplers plus boards and netting and a double-row scaffold weighs roughly 23 kg/m², so procuring on the tube figure alone under-orders by about thirty per cent. Boards are better counted by the piece: a 300×1500 deck is about 11 kg, which works out at 25 kg/m², not 15. Two sets of figures are given. The procurement set uses the actual board and netting weights for ordering, lifting and transport. The checking set uses the JGJ 130 self-weight values (0.30 kN/m² for boards, 0.01 kN/m² for netting) for standard stability and bearing checks. Do not mix them: buying on the checking set runs about twenty per cent high, while checking on the procurement set is unsafe. Tube is Φ48×3.5 at 3.84 kg/m; 3.0 mm wall is 13% lighter for the same length. Board area is perimeter × scaffold width × boarded levels, not every lift over the full height — a 20 m scaffold normally carries two boarded working levels. The main result rows exclude guard rails, toe boards, base plates and live load. The take-off applies to double-row facades only; for single-row and internal scaffolds use the rate-table rows above. The last four rows are a member-by-member take-off: standards, ledgers, transoms, base ledgers, bracing, transverse diagonals, ties and guard rails are counted individually for the layout you pick, rather than multiplying an area by a rate — on small elevations the end members weigh heavily and the rate method understates them. The two sets are different accounts: the rate table is for pricing and claims, the take-off is for cutting. A 5-15% gap between them is normal. For four sides (atrium, shaft) the perimeter is taken as 2 x (length + width) automatically, but bracing then has to run on all four faces, so each metre of length carries about 10% more than a single wall — the frame is closed, so it genuinely takes more. The design must be prepared to JGJ 130 by a qualified engineer.

Next up: Scaffold Tie Calculator · Formwork Turnover Calculator

Formula

Developed lengthL = 2 x (length + width); L = the wall length for a single wall
Scaffold areaA = developed length × height
Take-off tube per m²standards + ledgers + transoms + base ledgers + bracing + diagonals + ties + rails, summed and divided by area
Take-off couplers per m²right-angle + sleeve + swivel (incl. 3% wastage) divided by area
Steel tubeW = A × kg per m² × type factor
Tube countn = W ÷ 23.04 kg (6 m stock length)
CouplersN ≈ A × 3.0 × type factor
Coupler weightW_c = N × 1.34 kg
Board areaA_board = perimeter × scaffold width × boarded levels × type factor
Board weightW_b = A_board × unit mass (25 perforated, 30.6 pressed steel, 30 timber, 12 bamboo kg/m²)
Perforated deck piecesn ≈ A_board ÷ 0.45 m² (one 300×1500 board, about 11 kg)
Netting weightW_n = A × 1.05 × unit mass (0.21 actual, 1.02 code value kg/m²)
Total (procurement)W = W_tube + W_c + W_b + W_n at actual unit masses
Total (checking)W = W_tube + W_c + W_b + W_n at code values
Liftslifts = ceil(height ÷ 1.8)
An 80 m perimeter at 20 m high, 1.05 m wide with two boarded levels of perforated steel deck, gives 1,600 m². Bare tube at 16.5 kg/m² is 26.4 t; add 4,800 couplers (6.43 t), 168 m² of boards (4.20 t, 374 pieces of 300×1500) and 1,680 m² of netting (0.35 t) for about 37.4 t to procure, or 23.4 kg/m². Checked at the JGJ 130 self-weight values (0.30 kN/m² boards, 0.01 kN/m² netting) the same scaffold is 39.7 t, or 24.8 kg/m².

How to work it out

  1. Measure the outer face line of the external wall — not the building perimeter and not the grid line. Balconies, canopies and projecting eaves are measured on their own outer face.
  2. Set the height: external ground level to the underside of the eaves; up to the top of the parapet where there is one; to the eaves, not the ridge, on pitched roofs.
  3. Scaffold area = outer face length × height. Openings and balconies are not deducted — this is where scaffold measurement differs fundamentally from floor area.
  4. Take steel content by system: a double-row ground-supported scaffold runs 15.5-17.5 kg/m² (about 4.1-4.5 m of tube per m²), single row about 11-12 kg/m², and a full scaffold depends on standard spacing — roughly 35-40 kg/m² at 1.2 m spacing and 1.5 m lifts. The figure already covers standards, ledgers, bracing and base rails.
  5. Total steel = area × content; couplers at three per square metre of elevation, which is the same thing as 180-200 per tonne of tube — about four couplers per six-metre length. Decking by laid area, normally one working lift plus one protective lift.

Where it goes wrong

Material and cost

Scaffold complete (tube and coupler hire plus erection and dismantling) 20-45 CNY/m², including netting and decking. Tube hire about 4-6 CNY/m per month, couplers 0.3-0.5 each per month.

On site

Basis

FAQ

Is scaffold area measured on the wall face or the projection?
External scaffolding is the outside perimeter multiplied by the scaffold height, which is the vertical projection of the wall. Openings are not deducted. Single-row and double-row are separate rate items: both take the same vertical projection, it is not halved — the unit rate is what differs, and only some regional schedules apply a factor to the single-row item instead. Internal scaffolds are measured by wall projection, and full-hall scaffolds by internal floor area.
When must a double-row scaffold be used?
Single-row scaffolding is limited to 24 m and only where the wall can take reliable ties. Above 24 m a double-row system is required. In China, ground-supported tube scaffolding at 24 m or more is classified as high-risk work needing an expert-reviewed method statement, and above 50 m cantilevered or climbing systems must be used.
How much tube and how many couplers per square metre?
For a double-row ground-supported scaffold at 1.5 m bays, 1.05 m width and 1.8 m lifts, a member-by-member take-off gives: standards 2 rows / 1.5 = 1.33 m per m2; ledgers 2 runs / 1.8 = 1.11; transoms one per node x 1.25 m = 0.46, subtotal 2.91 m per m2. That counts three items only: standards, ledgers and transoms. Base ledgers 0.10, bracing and transverse diagonal braces 0.85, ties 0.03, guard rails and toe boards 0.20 are all still missing, and a full take-off gives 4.23 m per m2 (a closed scaffold on a 100 m perimeter at 20 m high, which is what the take-off rows on this page report; the same layout on a single wall gives 3.85, because the end adds a standard and bracing is shorter). The rate table works the other way: 16.5 kg per m2 divided by 3.84 kg/m gives 4.30 m per m2. So the three figures each have a job: 2.91 counts three items, 4.23 counts everything member by member, 4.30 is back-calculated from the rate table — cut to 4.23, price and order at 4.30. Couplers behave the same way: 2.9 per m2 node by node versus the 3.0 per m2 procurement factor used in the result rows (N = A x 3.0). Tightening the bays to 1.2 m raises the full take-off to about 4.81 m and 3.46 couplers per m2. All figures are on the elevation projection, not floor area. Note that this tool sizes couplers as elevation area x 3.0 (see the N = A x 3.0 row), 3% above the node-by-node 2.9: one tonne of 742 right-angle couplers covers 256 m2 at 2.9 but 247 m2 at 3.0, and ordering must use 247. The two numbers are a counted value versus a rounded procurement value, not a contradiction. All figures are on the elevation projection, not floor area.
Is it 4 m of tube per square metre or more than 5? Which figure is right?
Both are right; they stop at different points, and the variable is layout density, not height. Taking a 100 m perimeter at 20 m high and counting node by node: (1) 1.8 m bays / 1.8 m lifts / single mid-rail (the widest spacing JGJ 130 allows): bare tube 2.92 m per m2, 3.62 with bracing, and 3.80 once guard rails and toe boards are added (3.6 m per metre of perimeter, 0.18 per m2 at this height). (2) 1.5 m bays / 1.5 m lifts / double mid-rail (four ledgers per lift): standards 1.34 plus ledgers 2.67 = 4.01 — that is where the familiar "4 metres" comes from, but it counts standards and ledgers only. Add infill transoms 0.63, base ledgers 0.07, rails and toe boards 0.18 and bracing 0.85, and it becomes 5.90 m per m2, 22.7 kg per m2. The rule to remember: the per-m2 figure tracks the layout, hardly the height — going from 12 m to 48 m only takes it from 3.9 down to 3.5 (−12%), while one extra mid-rail at 1.5 m lifts adds 1.33 m per m2 (+33%), or 1.11 at 1.8 m lifts. So do not order off the "4 metres" figure: on a double mid-rail layout it will come up about thirty per cent short. Fix the bays, the lifts, the number of mid-rails, and whether bracing and rails are included, before you order.
Why not estimate couplers by weight or per tube?
Couplers follow the intersections of members, not the mass. A single 6 m standard crosses three or more lifts and needs a coupler to a ledger and a transom at each lift, so on its own it takes six or more. But standards are only about a third of the tube in a scaffold; ledgers, transoms and bracing need just one or two per six metres. Applying the standard's 6.5 to the whole scaffold overstates couplers by more than fifty per cent. Count node by node, or use an area rule such as three couplers per square metre.
How much does a square metre of scaffolding actually weigh?
For a double-row scaffold at 1.5 m bays, 1.05 m width, 1.8 m lifts and two boarded levels of perforated steel deck: about 16.2 kg/m² of bare tube, 4.0 of couplers, 2.6 of boards (two levels at 1.05 m wide over 20 m of height, at 25 kg/m²) and 0.2 of netting, so roughly 23 kg/m² to procure. The 16.5 figure commonly quoted is tube only and cannot be used for foundation loads, lifting weights or total procurement. Keep two sets apart: the JGJ 130 values of 0.30 kN/m² for boards and 0.01 kN/m² for netting are design self-weights and much heavier than the real product — the same scaffold checks out at about 25 kg/m². The gap looks small only because just two levels are boarded; board every lift and the same 22% turns into more than 5 kg/m². Use code values to check, actual values to buy, never the other way round. A ringlock scaffold at normal spacing weighs about 20 kg/m² because it has no couplers and fewer tubes, but tightening to 0.9 m bays and 1.5 m lifts pushes it back to about 27 kg/m². What ringlock saves is steel, not boards and netting.
How much railing and toe board per square metre?
Separate the two bases. Per metre of facade per working level, JGJ 130-2011 clause 6.2.1 requires two guard rails outside the working level, the top rail 1.2 m above the surface with a mid rail at half height; each is a 1 m length of 48x3.5 tube, so 2 x 3.84 = 7.68 kg per metre of width. The toe board must be at least 180 mm high: 0.18 x 0.015 x 600 = 1.62 kg/m. One level totals 9.30 kg/m. A facade scaffold only boards two working levels, so 9.30 x 2 = 18.60 kg per metre of width for the whole scaffold, and that figure is independent of the scaffold height: a 50 m long wall needs 930 kg whether it is 12 m or 48 m tall. Per square metre it is 18.60 divided by the height: 1.55 kg/m2 at 12 m, 0.775 at 24 m and only 0.39 kg/m2 at 48 m. Four times the height means a quarter of the rate. Order and stock on the per-metre figure, price and settle on the per-square-metre one. The result rows on this page exclude rails and toe boards, so add this item separately.
How much does one coupler weigh, and how many are there in a tonne?
Two figures measure two different things and must not be swapped. 1.35 kg is the design value: JGJ 130-2011 Annex A lists 13.2 N for a right-angle coupler, 14.6 N swivel and 18.4 N sleeve, i.e. 1.35 / 1.49 / 1.88 kg. It comes from the mean of a 408-piece sample plus two standard deviations and exists to compute scaffold self-weight for structural checks — it is not an acceptance limit. 1.10 kg is the acceptance limit: GB/T 15831 requires a cast right-angle coupler for Φ48.3 tube to weigh at least 1.10 kg gross and 0.90 kg net, with swivel at 1.15 / 0.95 and sleeve at 1.25 / 1.15. The 0.25 kg difference is mostly bolts and nuts, which carry no load. So a tonne of right-angle couplers is 742 pieces at the design 13.2 N (1.347 kg), but 909 pieces at the 1.10 kg acceptance limit — a gap of 167. Reject goods against 1.35 kg and compliant stock gets sent back; design self-weight against 1.10 kg and you understate it by a fifth. In jin: 1.10 kg is 2.2 jin, while the 1.35 kg design value is 2.7 jin.

What to calculate next

These jobs are done back to back on site — follow the steps to work through the whole sequence.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Scaffolding Calculator. 2026-10-25. https://jianzhujisuan.com/en/scaffolding

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.