Scaffolding Calculator
Enter the scaffolded length and height (plus the second side for four sides) to get the area, tube, coupler and board quantities.
Also known as scaffold tube and fitting · scaffold material takeoff · tube and coupler
With the default inputs: Length scaffolded 80 m · Second side 0 m · Scaffold height 20 m etc.Scaffold area 1600.0 m²It is 4.0 metres per m² or 5.9 — both are right. Counting standards and mid-rails only gives 4.01 m, the familiar "4 metres per square"; add base ledgers, bracing, ties and guard rails with toe boards and a member take-off gives 5.90 m. Counting standards, ledgers and transoms alone gives 2.91 m — the "3 metres per square" seen online simply omits base ledgers and bracing. The per-m² figure tracks layout, hardly height: from 12 m to 48 m it only falls from 3.9 to 3.5. Couplers follow the layout: 2.6 per m² at 1.5x1.8 with one mid-rail, 4.3 at 1.5x1.5 with two; the 3.0 in the result rows is a rounded allowance, so order 4.3 on a double mid-rail. For four sides (atrium, shaft) enter length and width and the perimeter becomes 2 x (length + width).
Use your own dimensions ↓Inputs
Result
| Lifts @1.8 m | 12lifts |
| Scaffold area | 1600.0m² |
| Perimeter | 80.0m |
| Steel tube (bare) | 26.40t |
| 6 m tubes | 1146bars |
| Couplers per 6 m tube | 4.19pcs |
| Couplers (about 3.0 per m²) | 4,800pcs |
| Coupler weight (1.34 kg each) | 6.43t |
| Board area (2 levels × 1.05 m) | 168.0m² |
| Board weight (25 kg/m²) | 4.20t |
| Safety netting | 1680.0m² |
| Netting weight (about 0.21 kg/m² actual) | 0.35t |
| Total self-weight (for procurement) | 37.38t |
| Self-weight per m² (procurement) | 23.4kg/m² |
| Self-weight at code values (for checking) | 39.69t |
| Self-weight per m² (design values) | 24.8kg/m² |
| Wall ties (3 lifts × 3 bays) | 72pcs |
| Take-off tube per m² (1.5 bays, 1.8 lifts, one mid-rail) | 3.85m/m² |
| Take-off tube total (with bracing and rails) | 23.62t |
| Take-off couplers per m² | 2.58pcs/m² |
| Take-off couplers total (incl. 3% wastage) | 4,124pcs |
How this is worked out
The 16.5 kg/m² figure is bare tube only — standards, ledgers and bracing. Add about 4.0 for couplers plus boards and netting and a double-row scaffold weighs roughly 23 kg/m², so procuring on the tube figure alone under-orders by about thirty per cent. Boards are better counted by the piece: a 300×1500 deck is about 11 kg, which works out at 25 kg/m², not 15. Two sets of figures are given. The procurement set uses the actual board and netting weights for ordering, lifting and transport. The checking set uses the JGJ 130 self-weight values (0.30 kN/m² for boards, 0.01 kN/m² for netting) for standard stability and bearing checks. Do not mix them: buying on the checking set runs about twenty per cent high, while checking on the procurement set is unsafe. Tube is Φ48×3.5 at 3.84 kg/m; 3.0 mm wall is 13% lighter for the same length. Board area is perimeter × scaffold width × boarded levels, not every lift over the full height — a 20 m scaffold normally carries two boarded working levels. The main result rows exclude guard rails, toe boards, base plates and live load. The take-off applies to double-row facades only; for single-row and internal scaffolds use the rate-table rows above. The last four rows are a member-by-member take-off: standards, ledgers, transoms, base ledgers, bracing, transverse diagonals, ties and guard rails are counted individually for the layout you pick, rather than multiplying an area by a rate — on small elevations the end members weigh heavily and the rate method understates them. The two sets are different accounts: the rate table is for pricing and claims, the take-off is for cutting. A 5-15% gap between them is normal. For four sides (atrium, shaft) the perimeter is taken as 2 x (length + width) automatically, but bracing then has to run on all four faces, so each metre of length carries about 10% more than a single wall — the frame is closed, so it genuinely takes more. The design must be prepared to JGJ 130 by a qualified engineer.
Next up: Scaffold Tie Calculator · Formwork Turnover Calculator
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Developed length | L = 2 x (length + width); L = the wall length for a single wall |
| Scaffold area | A = developed length × height |
| Take-off tube per m² | standards + ledgers + transoms + base ledgers + bracing + diagonals + ties + rails, summed and divided by area |
| Take-off couplers per m² | right-angle + sleeve + swivel (incl. 3% wastage) divided by area |
| Steel tube | W = A × kg per m² × type factor |
| Tube count | n = W ÷ 23.04 kg (6 m stock length) |
| Couplers | N ≈ A × 3.0 × type factor |
| Coupler weight | W_c = N × 1.34 kg |
| Board area | A_board = perimeter × scaffold width × boarded levels × type factor |
| Board weight | W_b = A_board × unit mass (25 perforated, 30.6 pressed steel, 30 timber, 12 bamboo kg/m²) |
| Perforated deck pieces | n ≈ A_board ÷ 0.45 m² (one 300×1500 board, about 11 kg) |
| Netting weight | W_n = A × 1.05 × unit mass (0.21 actual, 1.02 code value kg/m²) |
| Total (procurement) | W = W_tube + W_c + W_b + W_n at actual unit masses |
| Total (checking) | W = W_tube + W_c + W_b + W_n at code values |
| Lifts | lifts = ceil(height ÷ 1.8) |
How to work it out
- Measure the outer face line of the external wall — not the building perimeter and not the grid line. Balconies, canopies and projecting eaves are measured on their own outer face.
- Set the height: external ground level to the underside of the eaves; up to the top of the parapet where there is one; to the eaves, not the ridge, on pitched roofs.
- Scaffold area = outer face length × height. Openings and balconies are not deducted — this is where scaffold measurement differs fundamentally from floor area.
- Take steel content by system: a double-row ground-supported scaffold runs 15.5-17.5 kg/m² (about 4.1-4.5 m of tube per m²), single row about 11-12 kg/m², and a full scaffold depends on standard spacing — roughly 35-40 kg/m² at 1.2 m spacing and 1.5 m lifts. The figure already covers standards, ledgers, bracing and base rails.
- Total steel = area × content; couplers at three per square metre of elevation, which is the same thing as 180-200 per tonne of tube — about four couplers per six-metre length. Decking by laid area, normally one working lift plus one protective lift.
Where it goes wrong
- Deducting windows and doors — scaffolding is measured on the vertical projection of the facade and the scaffold still runs past every opening.
- Using floor area as scaffold area — floor area projects the structural envelope horizontally, scaffolding projects the outer face vertically; the difference is height plus projecting elements.
- Measuring height only to the eaves — parapets measure to their top, and rooftop plant such as tanks and lift motor rooms needs separate consideration.
- Ignoring the high-level allowance — many regions add a premium above 24 m, and above 50 m the scaffold is a major hazard installation needing expert review.
Material and cost
Scaffold complete (tube and coupler hire plus erection and dismantling) 20-45 CNY/m², including netting and decking. Tube hire about 4-6 CNY/m per month, couplers 0.3-0.5 each per month.
On site
- Ground-supported scaffolding over 24 m is a major hazard installation and over 50 m needs expert review; the method statement and acceptance records are mandatory documents.
- Ties must connect to structure, never to window frames, balustrades or pipes; three lifts by three bays is the usual spacing.
- Hardstand and drain the scaffold base, and use sole plates and base jacks. Standing standards directly on backfill is the leading cause of collapse.
Basis
- EN 12811-1:2003 Temporary works equipment — Scaffolds — Performance requirements and general design
- BS 5975:2019 Code of practice for temporary works procedures
- NASC TG20:21 Guide to good practice for scaffolding with tubes and fittings
- OSHA 29 CFR 1926 Subpart L (Scaffolds) — for US projects
FAQ
Is scaffold area measured on the wall face or the projection?
When must a double-row scaffold be used?
How much tube and how many couplers per square metre?
Is it 4 m of tube per square metre or more than 5? Which figure is right?
Why not estimate couplers by weight or per tube?
How much does a square metre of scaffolding actually weigh?
How much railing and toe board per square metre?
How much does one coupler weigh, and how many are there in a tonne?
What to calculate next
These jobs are done back to back on site — follow the steps to work through the whole sequence.
Scaffolding: quantity to costStep 1 of 5
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Scaffolding Calculator. 2026-10-25. https://jianzhujisuan.com/en/scaffolding